Watches › Siting Watch › Maine
Siting Watch in Maine
Data centers, battery storage, solar and wind: the rules each local government is writing, the pauses it has voted and the projects on its agendas. Read every day from the agendas and minutes of more than 12,600 governments.
By use
One record per government and use. Pick a use for its rules, pauses and projects.
| Use | Rules proposed | Rules adopted | Pauses proposed | Pauses in force | New, 30 days |
|---|---|---|---|---|---|
| Data centers | 21 | 0 | 21 | 5 | 2 |
| Battery storage | 2 | 0 | 0 | 0 | 0 |
| Solar | 7 | 1 | 3 | 2 | 0 |
| Wind turbines | 0 | 0 | 0 | 0 | 0 |
Where
Most records: Pennsylvania (417), New York (281), Michigan (279).
Pick a state for its records. Pick it again for every state.
A county brief
Every rule, pause and project of one county on a page made for print.
Votes and hearings ahead
Rules and pauses on an agenda in the next 30 days in Maine, soonest first.
- Nov 24On agenda
Would establish conditional use standards for biosolids thermal processing facilities and data centers in IB z
Newest
By the first agenda each was on.
- Nov 17
Data center policy or ordinance under consideration
- Nov 12
“Article 5 would enact the “Town of Eliot Data Center Moratorium” ordinance”
- Oct 21
Town discussion of data center rules
- Oct 21
“…BUSINESS: Order No. 26-090. First reading on the request to repeal the 180-day temporary moratorium entitled “Town of Scarborough Ordinance Establishing a Temporary Moratorium on Data Centers,” that was approved by the…”
- Oct 19
Requests land use code amendments regulating data centers
- Nov 10
“Revisions to Moratorium Ordinance on Data Center”
- Oct 8
Staff memo on possible approaches and standards for data centers
- Oct 15
“Ordinance on Data Center Moratorium”
- Oct 5
Continuation of solar ordinance work alongside subdivision ordinance
- Oct 13
“The purpose of this Public Hearing is to receive public comment regarding a proposed Data Center Moratorium.”
- Sep 21
“Data Center Moratorium. If it is of interest, the Board could tentatively plan to place the question on the June 2027 Warrant”
- Sep 17
Town consideration of a data center ban
- Nov 4
“Public Hearing for the Proposed Data Center Moratorium Ordinance is scheduled for Tuesday, Nov. 17, 2026”
- Nov 17
“Review the ORDINANCE TO ESTABLISH A TEMPORARY MORATORIUM ON DATA CENTERS and discuss a Data Center Ordinance”
- Nov 24On agenda
Would establish conditional use standards for biosolids thermal processing facilities and data centers in IB z
- Nov 10
“Data Center Moratorium: Building Permit Ordinance”
- Nov 9
“the City does hereby declare a moratorium on the location, operation, permitting, and licensing of data storage and data center facilities”
- Sep 8
Review and possibly update town ordinances on data centers
- Oct 5
Public hearing on amending land use code to restrict large-scale data centers
- Nov 9
“Solar Moratorium Next Steps”
- Sep 16
“Data Center Moratorium and Sub-Committee Appointments”
- Sep 2
Proposed ban on e-commerce facilities and data centers
- Aug 19
“citizen request for a discussion on a moratorium for Data Centers in Whitefield”
- Sep 1
“certify the Data Center Moratorium Ordinance and place the question on the November 3, 2026 Special Town Meeting Warrant”
- Aug 13
Update on data center rules
- Aug 12
“Consider a Temporary Moratorium on Data Centers and Associated Infrastructure”
- Sep 8
Discussion on drafting a battery storage ordinance
- Sep 16
Proposed town ordinances on community septic and data centers
- Aug 4
Possible town solar energy systems ordinance; council asked if it wants to pursue it
- Aug 3
Data center workshop packet for town code (workshop discussion)
- Oct 7
Discuss amendments to ordinance prohibiting large-scale data centers across all zones
- Aug 11
Amends Land Use Code solar energy systems section 442
- Jul 28
Data center zoning provisions for public hearing scheduling
- Jul 22
Creates committee to review data center ordinance
- Aug 18
“g. Moratorium on Data Centers”
- Aug 4
“enact a citizen-initiated ordinance instituting a 180-day moratorium on data centers”
- Oct 15
“An Ordinance to Establish a Temporary Moratorium on Data Centers”
- Jul 6
Review and revise land use and site plan ordinances to allow energy storage systems
- Sep 22
“public hearing to discuss the draft Data Center Moratorium Ordinance”
- Jul 14
“Solar Moratorium: Certification”
How we count
A rule is the government's own ordinance, code or zoning text on the use: where it may go and under what conditions. A pause is a moratorium on new applications. A project is one applicant's case: a rezoning, a site plan, a special use permit. The AI reads every agenda line that names the use and keeps the ones about the government's own rule or pause; each record is one government and one use, and links to the line it comes from. A status can lag a vote by days, and a line can be read wrong: open the line before you rely on it. The spreadsheets are free; please credit GovMeet.