Watches › Siting Watch › Kansas
Siting Watch in Kansas
Data centers, battery storage, solar and wind: the rules each local government is writing, the pauses it has voted and the projects on its agendas. Read every day from the agendas and minutes of more than 12,600 governments.
By use
One record per government and use. Pick a use for its rules, pauses and projects.
| Use | Rules proposed | Rules adopted | Pauses proposed | Pauses in force | New, 30 days |
|---|---|---|---|---|---|
| Data centers | 15 | 0 | 9 | 1 | 0 |
| Battery storage | 8 | 0 | 3 | 1 | 1 |
| Solar | 0 | 0 | 4 | 0 | 0 |
| Wind turbines | 2 | 0 | 1 | 0 | 0 |
Where
Most records: Pennsylvania (417), New York (281), Michigan (279).
Pick a state for its records. Pick it again for every state.
A county brief
Every rule, pause and project of one county on a page made for print.
Votes and hearings ahead
Rules and pauses on an agenda in the next 30 days in Kansas, soonest first.
- Nov 24On agenda
Draft standards for data storage centers and other uses; BESS provisions left unchanged for now
- Nov 24On agenda
Draft standards for data centers as conditional use in unincorporated county; noise provisions
Newest
By the first agenda each was on.
- Nov 24On agenda
Draft standards for data centers as conditional use in unincorporated county; noise provisions
- Nov 24On agenda
Draft standards for data storage centers and other uses; BESS provisions left unchanged for now
- Nov 5
Solar, wind, and battery storage rules (topic heading only)
- Sep 2
Temporary moratorium resolution on special use permits for data centers; no lasting rules shown
- Sep 2
“Granting A Temporary Moratorium On The Planning, Establishment, Construction, Application For Or Permitting Of Any Special Use Permits For Data Centers”
- Aug 26
New business item on data centers at planning and zoning meeting
- Nov 16
Consideration of new zoning regulations Article 32 for battery energy storage systems
- Aug 26
Ballot question prohibiting Tier 2 and Tier 3 battery energy storage systems
- Aug 13
“establishing a temporary moratorium on new data center applications in Shawnee County”
- Aug 10
Data center rules (details not stated)
- Aug 26
Submits ordinance prohibiting high impact data centers to voters in November
- Jul 27
Discussion and review of county data center policy
- Jul 20
“Determination on Moratorium for Wind Farms, Solar Farms, Battery Energy Storage Systems (BESS), and Data Centers”
- Jul 20
“Determination on Moratorium for Wind Farms, Solar Farms, Battery Energy Storage Systems (BESS), and Data Centers”
- Jul 20
“Determination on Moratorium for Wind Farms, Solar Farms, Battery Energy Storage Systems (BESS), and Data Centers”
- Nov 16
Enrollment of ordinance prohibiting installation and operation of Tier 2 and Tier 3 battery energy storage sys
- Nov 16
Prohibits installation and operation of High Impact Data Centers and Tier 2/3 battery storage citywide
- Jul 7
“Data Center: Moratorium”
- Jun 22
“A RESOLUTION ESTABLISHING A TEMPORARY MORATORIUM ON THE ACCEPTANCE, PROCESSING, AND APPROVAL OF CERTAIN APPLICATIONS FOR ALTERNATIVE ENERGY FACILITIES AND DATA CENTER DEVELOPMENTS”
- Jun 22
“A RESOLUTION ESTABLISHING A TEMPORARY MORATORIUM ON THE ACCEPTANCE, PROCESSING, AND APPROVAL OF CERTAIN APPLICATIONS FOR ALTERNATIVE ENERGY FACILITIES AND DATA CENTER DEVELOPMENTS”
- Jul 2
Resolution setting application fees and escrow for energy storage conditional use permits
- Jul 2
Application fees, escrow deposits and cost reimbursement for data center CUP applications
- Aug 5
“providing for a moratorium on applications for battery energy storage systems”
- Jun 1
“imposing a moratorium on the acceptance or consideration of applications for data centers”
- Oct 15
“Data Center and BESS Moratorium Extension”
- Oct 15
“Data Center and BESS Moratorium Extension”
- Aug 19
“providing for a moratorium on applications for data centers in the unincorporated area”
- May 19
“Moratorium for Data Center Commission Discussion”
- May 4
Adoption of special use permit application forms for commercial wind energy conversion systems
- Nov 10
Follow-up discussion on data center regulations
- Apr 20
Adopt special use permit application form for data centers and amend base form
- Jun 22
Planning department agenda item on data center and battery storage regulations
- May 4
Work session on data centers and battery energy storage systems regulations
- Apr 13
“zoning change and solar moratorium update”
- Oct 22
Work session on large scale data center regulations
- Nov 19
Continued discussion of draft data center regulations from hearing
- Jun 10
Data center regulations work session on development regulations and tax impact
- Mar 10
“Land Development Tricia Webb Data Center Moratorium”
- Feb 23
Commission to discuss text amendments on wind energy conversion systems, Article 27
- Feb 2
“Resolution for extension of temporary moratoriums: Battery Energy Storage Systems; Data Centers; and Hydrogen Energy Facilities”
How we count
A rule is the government's own ordinance, code or zoning text on the use: where it may go and under what conditions. A pause is a moratorium on new applications. A project is one applicant's case: a rezoning, a site plan, a special use permit. The AI reads every agenda line that names the use and keeps the ones about the government's own rule or pause; each record is one government and one use, and links to the line it comes from. A status can lag a vote by days, and a line can be read wrong: open the line before you rely on it. The spreadsheets are free; please credit GovMeet.