Siting Watch in Louisiana

Data centers, battery storage, solar and wind: the rules each local government is writing, the pauses it has voted and the projects on its agendas. Read every day from the agendas and minutes of more than 12,600 governments.

7governments writing rules
0rules adopted
5pauses in force
0on an agenda in the next 30 days

By use

One record per government and use. Pick a use for its rules, pauses and projects.

UseRules proposedRules adopted Pauses proposedPauses in forceNew, 30 days
Data centers30100
Battery storage00010
Solar50030
Wind turbines00010

Where

Most records: Pennsylvania (417), New York (281), Michigan (279).

Pick a state for its records. Pick it again for every state.

1 to 45 to 1415 or more

A county brief

Every rule, pause and project of one county on a page made for print.

Newest

By the first agenda each was on.

  1. Sep 14
    Parish of Washington, LAPause in forceWind

    “Amending ​Resolution No. 26-1506, Placing a Moratorium on the Approval ​and/or Permitting of All Solar Panel Farms”

    On 1 meeting

  2. Oct 19
    Parish of St Mary, LARule proposedSolar

    Proposed text amendment to unified development code for solar farm developments

    On 3 meetings · first Aug 26 · this government

  3. Oct 13
    City of New Orleans, LARule proposedData centers

    Text amendment defining data centers, deciding permitted or conditional zones, and design standards

    On 2 meetings · first Aug 25 · this government

  4. Jul 29
    Parish of St Mary, LAPause in forceSolar

    “Resolution repealing the temporary moratorium on the development, establishment, construction, and expansion of utility-scale solar energy facilities”

    On 2 meetings · first Jul 22

  5. Sep 28
    Parish of Washington, LAPause in forceBattery storage

    “Adopt a Resolution Extending the Moratorium on the Approval ​and/or Permitting of Battery Energy Storage Systems (BESS)”

    On 4 meetings · first Jul 9

  6. Sep 14
    Parish of Washington, LAPause in forceSolar

    “Amending ​Resolution No. 26-1506, Placing a Moratorium on the Approval ​and/or Permitting of All Solar Panel Farms”

    On 3 meetings · first Jul 9

  7. Jun 4
    Parish of St Tammany, LARule proposedSolar

    Amends zoning Chapter 400 to update existing regulations for solar farm uses

    On 1 meeting · this government

  8. Apr 20
    Parish of Natchitoches, LARule proposedData centers

    Adds data centers as permitted by-right use in I-2 districts

    On 2 meetings · first Apr 20 · this government

  9. Apr 6
    Parish of St Charles, LAPause proposedData centers

    “enact a MORATORIUM on the permitting, consideration, approval, location, construction, and/or installation of any Data Center facilities for a period of 12 months”

    On 2 meetings · first Mar 16

  10. Jun 1
    Parish of St Charles, LARule proposedData centers

    Adds data center definition, permits them in M-1 and M-2 districts, adds requirements

    On 5 meetings · first Mar 16 · this government

  11. Mar 12

    “Resolution Expressing The Desire Of The West Baton Rouge Parish Council To Lift A Moratorium On Solar Panel Farms”

    On 1 meeting

  12. Jun 1

    Receive public input on proposed solar farm ordinance

    On 5 meetings · first Feb 2 · this government

  13. Mar 16
    Parish of St Charles, LARule proposedSolar

    Adds development standards for large solar energy systems in zoning ordinance

    On 5 meetings · first Dec 15, 2025 · this government

  14. Oct 14, 2025
    Parish of St Helena, LARule proposedSolar

    St. Helena Parish solar energy/solar farm permitting ordinance

    On 3 meetings · first Sep 23, 2025 · this government

How we count

A rule is the government's own ordinance, code or zoning text on the use: where it may go and under what conditions. A pause is a moratorium on new applications. A project is one applicant's case: a rezoning, a site plan, a special use permit. The AI reads every agenda line that names the use and keeps the ones about the government's own rule or pause; each record is one government and one use, and links to the line it comes from. A status can lag a vote by days, and a line can be read wrong: open the line before you rely on it. The spreadsheets are free; please credit GovMeet.