Watches › Siting Watch › Michigan
Siting Watch in Michigan
Data centers, battery storage, solar and wind: the rules each local government is writing, the pauses it has voted and the projects on its agendas. Read every day from the agendas and minutes of more than 12,600 governments.
By use
One record per government and use. Pick a use for its rules, pauses and projects.
| Use | Rules proposed | Rules adopted | Pauses proposed | Pauses in force | New, 30 days |
|---|---|---|---|---|---|
| Data centers | 98 | 0 | 95 | 39 | 20 |
| Battery storage | 16 | 0 | 12 | 3 | 2 |
| Solar | 5 | 0 | 5 | 2 | 1 |
| Wind turbines | 0 | 0 | 3 | 1 | 1 |
Where
Most records: Pennsylvania (417), New York (281), Michigan (279).
Pick a state for its records. Pick it again for every state.
A county brief
Every rule, pause and project of one county on a page made for print.
Votes and hearings ahead
Rules and pauses on an agenda in the next 30 days in Michigan, soonest first.
- Nov 24On agenda
Public hearing on zoning text amendment regulating data centers
- Nov 24On agenda
Zoning text amendment for data centers
- Nov 24On agenda
Text amendment for roof mounted solar energy systems
Newest
By the first agenda each was on.
- Nov 18new
“b. Data Center Moratorium”
- Nov 18new
“would establish a six (6) month temporary moratorium on certain zoning approvals and applications related to High Resource Demand Facilities, including data centers”
- Nov 17
Revises zoning uses allowed for data centers in residential, commercial, and industrial districts
- Nov 17
Zoning ordinance amendment for data centers
- Nov 17new
“Update wording for zoning concerning data centers and solar/wind farms moratorium”
- Nov 17new
“Update wording for zoning concerning data centers and solar/wind farms moratorium”
- Nov 17new
“Update wording for zoning concerning data centers and solar/wind farms moratorium”
- Nov 16
Introduces zoning text amendments for data centers
- Nov 16new
“Extend Data Center Moratorium”
- Nov 12
County draft data center ordinance under Planning Commission review
- Nov 11
Unfinished business: ordinance for data center
- Nov 10
Amend zoning ordinance to regulate data centers
- Nov 10
Public hearing on data center zoning ordinance amendments and moratorium
- Nov 10
“Discussion of Police Power Ordinances Establishing Data Center and Energy Systems Moratoria”
- Nov 10
“Discussion of Police Power Ordinances Establishing Data Center and Energy Systems Moratoria”
- Nov 9
“Establishing a Temporary Moratorium on the Acceptance, Processing, Review, or Approval of New Applications for Mega Data Centers”
- Nov 12
Planning commission feedback on land use regulation options for data centers
- Nov 9
Discussion of zoning ordinance changes for data centers
- Nov 9
“place a moratorium on data centers being built on county land until further research can be done”
- Nov 7
Proposes lowering permitted noise ceiling 5 dB for data centers with pure tones
- Oct 27
“Moratorium on BESS”
- Oct 27
“Moratorium on Data Centers”
- Nov 9
Joint meeting to discuss a proposed data center ordinance
- Oct 26
Data center ordinance on agenda for new business
- Oct 21
Draft ordinance for battery energy storage systems
- Oct 21
“1. BESS Moratorium”
- Oct 21
“look into leaf ordinance and moratorium on data centers”
- Nov 9
Update on township data center ordinance
- Nov 17
“Approve Resolution # 2026-02, A Resolution to Authorize a Temporary Moratorium on Data Centers”
- Oct 20
Refer data center and battery storage ordinance to Planning Commission
- Oct 20
Refers data center and battery storage ordinance to planning commission
- Oct 20
Updating zoning wording for data centers and solar/wind farms
- Oct 20
“Public Hearing and Consideration of a Zoning Ordinance Amendment. Temporary Moratorium Authority and Temporary Moratorium for Data Centers.”
- Oct 20
“Proposed Ord. 312 – Moratorium on Battery Storage Systems”
- Oct 20
“Data Center Moratorium”
- Oct 20
“Set public hearing for December 1st: Data Center moratorium”
- Oct 20
“Support for a one-year moratorium on new data center permitting and construction was discussed”
- Oct 19
“Resolution for a 180-Day Moratorium on the Building of Data Centers”
- Oct 19
Definitions for battery storage, data center and digital mining zoning amendments
- Oct 19
“Consider ordinance to enact a temporary moratorium on acceptance and/or processing of any applications for data centers”
How we count
A rule is the government's own ordinance, code or zoning text on the use: where it may go and under what conditions. A pause is a moratorium on new applications. A project is one applicant's case: a rezoning, a site plan, a special use permit. The AI reads every agenda line that names the use and keeps the ones about the government's own rule or pause; each record is one government and one use, and links to the line it comes from. A status can lag a vote by days, and a line can be read wrong: open the line before you rely on it. The spreadsheets are free; please credit GovMeet.