Watches › Moratorium Watch › Data centers › City of Hallowell
Data center moratorium
City of Hallowell, ME
- Status
- In force Adopted
- Pauses
- Data centers
- Seen
- 3 meetings, Sep 8, 2026 to Nov 9, 2026
- Decided
- Oct 13, 2026
Every meeting it was on
Newest first: one agenda line a meeting, with the words that show it.
- Nov 9, 2026Proposed · Meetings
“A moratorium is hereby imposed, effective immediately and applicable to the maximum extent permitted by law, on all proceedings, applications, petitions and requests for data storage or data center facilities”
- Oct 13, 2026Adopted · Meetings
“the City does hereby declare a moratorium on the location, operation, permitting, and licensing of data storage and data center facilities”
- Sep 8, 2026Proposed · Meetings
“institute an 180-day moratorium on all current or future data center projects”