16rules proposed0rules adopted3pauses in force1projects on agendas ahead

The government's own ordinance or zoning text. On an agenda ahead first, then the newest.

  1. Nov 24On agenda
    Prowers County, CORule proposed

    Public hearing on resolution extending moratorium on processing data center special use permits

    On 6 meetings · first Jun 23 · this government

  2. Nov 18
    Larimer County, CORule proposed

    Draft land use code regulations for data centers

    On 10 meetings · first Jan 26 · this government

  3. Nov 18
    Pueblo County, CORule proposed

    Text amendment adding use-specific standards for data centers in industrial uses

    On 2 meetings · first Sep 16 · this government

  4. Nov 10
    Boulder County, CORule proposed

    Public hearing on land use code text amendments related to data centers

    On 8 meetings · first May 26 · this government

  5. Nov 3
    Elbert County, CORule proposed

    Discussing possible county land use regulations for data centers and similar tech operations

    On 4 meetings · first Aug 10 · this government

  6. Oct 26
    City of Aurora, CORule proposed

    Amends Unified Development Ordinance section 146-3.2 on data centers in the permitted use table

    On 8 meetings · first Aug 10 · this government

  7. Oct 19
    Arapahoe County, CORule proposed

    Follow-up discussion on data center environmental and regulatory land development code updates

    On 1 meeting · this government

  8. Oct 13
    Grand County, CORule proposed

    Workshop on data center regulations among other topics

    On 3 meetings · first May 13 · this government

  9. Aug 25

    Update on town data center land use rules

    On 1 meeting · this government

  10. Aug 25

    Information on aligning data centers with Land Use Code and next steps

    On 1 meeting · this government

  11. Aug 18
    Morgan County, CORule proposed

    Zoning amendments related to data centers, continued public hearing

    On 6 meetings · first May 5 · this government

  12. Jul 13

    Consideration of data center development (unclear if rules)

    On 1 meeting · this government

  13. Jun 4

    Status and schedule updates on data center regulations

    On 1 meeting · this government

  14. May 13

    Initial report on regulating data centers in the Town

    On 1 meeting · this government

  15. Apr 23

    Draft water efficiency ordinance for data centers in City of Commerce

    On 1 meeting · this government

  16. Feb 17
    Logan County, CORule proposed

    Adopts regulations for issuing permits for data center facilities in unincorporated Logan County

    On 2 meetings · first Jan 20 · this government

How we count

A rule is the government's own ordinance, code or zoning text on the use: where it may go and under what conditions. A pause is a moratorium on new applications. A project is one applicant's case: a rezoning, a site plan, a special use permit. The AI reads every agenda line that names the use and keeps the ones about the government's own rule or pause; each record is one government and one use, and links to the line it comes from. A status can lag a vote by days, and a line can be read wrong: open the line before you rely on it. The spreadsheets are free; please credit GovMeet.