Watches › Moratorium Watch › Battery storage › Putnam County
Battery storage moratorium
Putnam County, GA
- Status
- In force Adopted
- Pauses
- Battery storage
- Seen
- 5 meetings, Aug 7, 2026 to Nov 6, 2026
- Decided
- Oct 21, 2026
- Ends
- Jan 20, 2027
Every meeting it was on
Newest first: one agenda line a meeting, with the words that show it.
- Nov 6, 2026Extension proposed · Board of Commissioners
“Resolution to Extend the Moratorium on Data Centers, Battery Storage Centers, and Solar Energy Systems”
- Oct 21, 2026Adopted · Board of Commissioners
“the commissioners approved a 3-month moratorium on Data Centers, Battery Storage Systems, and Solar Farms”
- Sep 4, 2026Extended · Board of Commissioners
“the Board voted for a 3-month moratorium on new solar farms, battery storage facilities, and data centers”
- Aug 18, 2026Discussion · Board of Commissioners
“during the 3-month moratorium (RG)”
- Aug 7, 2026Discussion · Board of Commissioners
“enact a moratorium of up to 12 months on Data Centers, BESS and Solar Farms”
The status comes from these lines: the AI says what each one did, and a vote the minutes record as passed counts as done. We may not yet have read every meeting. All meetings of Putnam County.