Agendaputnamcoga.api.civicclerk.comMinutesputnamcoga.api.civicclerk.comRecording ▸putnamcoga.portal.civicclerk.comAttachment260630 Section 66-121 Expansion of PUD DistrictsAttachmentStillwater - Phase 1 recordedAttachmentStillwater 04 - Quitclaim Deed (recorded)AttachmentStillwater Phase 1 - request for final plat inspAttachmentStillwater Phase 1 - request for final plat inspAttachmentStillwater Phase 1 utility As-BuiltsAttachmentStillwater Phase I Final Plat re-recordAttachment2026-08-26 Draft Technology Uses - PutnamAttachmentHarmony Farms Phase 3 agenda packageMeeting page ↗putnamcoga.portal.civicclerk.com
4 items on this agenda match the land-use topicsSubdivisions (2), Planned developments (1), Moratoriums (1), Data centers & plants (1)
Agenda items (25)Show only the 4 matching
- 1.Welcome - Call to Order p. 1
- 2.Approval of Agenda
- 3.Invocation - David Wofford, Eatonton First Methodist Church p. 1
- 4.Pledge of Allegiance (RG) p. 1
- 5.Special Presentation - Ovarian Cancer Awareness Month Proclamation p. 1
- 6.Proposed adoption of changes to the Putnam County Code of Ordinances - Chaper 18 - Section 18-36 (Adoption of technical codes) p. 1
- 7.Proposed adoption of changes to the Putnam County Code of Ordinances - Chapter 18 - Article IV (Public Nuisance Dwellings, Buildings, or Structures) (Repeal) p. 1
- 8.Proposed adoption of changes to the Putnam County Code of Ordinances - Chapter 66 - Section 66-121 (Expansion of PUD Districts) (New) p. 1
- 9.Public Comments
- 10.Consent Agenda a. Approval of Minutes - August 18, 2026 Regular Meeting (staff-CC) b. Approval of Minutes - August 27, 2026 Called Meeting (staff-CC) c. Approval of Minutes - August 27, 2026 Executive Session (staff-CC) d. Approval of Minutes - August 27, 2026 Town Hall Meeting (staff-CC) e. Approval of 2026 Alcohol Licenses (staff-CC) p. 1
- 11.Georgia Association of Zoning Administrators (GAZA) Report - Charles Gray p. 1
- 12.Request for Final Plat Subdivision Approval - Stillwater Lake Oconee-Phase 1 Revision (staff-P&D)
- 13.Request for Road Acceptance for Harmony Farms Subdivision Phase 3 - Harmony Farms Orchard and Harmony Grove Court (staff-PW) p. 1
- 14.Right-of-Way Permit Request by AT&T for work near 331 Harmony Road (staff-PW) p. 1
- 15.Authorization for Chairman to sign Resolution setting 2026 Mill Rate (staff-CM & Finance) p. 1
- 16.Approval of Budget Adjustment - Golf Course Clubhouse (repair roof leaks) (staff-CM) p. 1
- 17.Approval of Budget Adjustment - Public Works (roof replacement) (staff-CM) p. 1
- 18.Discussion and possible action on the Calendar Year Excess Annual Leave Conversion Option (staff-CM) - A provision in the County’s Personnel Policy allows employees the option of converting excess annual carry-over leave into their 457 DC Plan or their DB Plan. This option is “only provided if funds are available”. For calendar year 2025, the cost of the redeemed leave totaled $113,218.43 and was funded in January of 2026. If this option is to be funded for the 2026 calendar year, funding would need to be identified and allocated by the Board. If it is not to be funded, then timely notification to the employees would be necessary so that they could utilize their accrued leave that exceeds the allowed carryover amount. Direction is needed from the Board on this item. Carry Over Annual Leave Putnam County provides access to retirement investment with the option of converting excess annual … p. 1
- 19.Adoption of Revised Personnel Policy (staff-CM) p. 1
- 20.Authorization for staff to obtain Pay Classification Study (staff-CM) p. 1
- 21.…consultation on the draft Solar Farms, Battery Storage, and Data Center ordinances, ongoing ordinance revisions, and set the date for the second Town Hall (RG) - At the Board of Commissioners meeting held on August 7, the Board voted for a 3-month moratorium on new solar farms, battery storage facilities, and data centers. The Board has a draft ordinance to regulate all three technologies, but public interest in these matters merits more time for citizen consultation. A relatively short moratorium is designed to drive the process forward, take advantage of heightened citizen interest, and get an improved ordinance on the books so the county can be positioned to take advantage of the benefits of these technologies and avoid the pitfalls. At the BOC meeting on September 4, the Board will discuss and potentially approve some additional steps in the consultation process, including: •… p. 2