Watches › Moratorium Watch › Data centers › Meriwether County
Data center moratorium
Meriwether County, GA
- Status
- In force Adopted
- Pauses
- Data centers
- Seen
- 3 meetings, Feb 24, 2026 to Oct 27, 2026
- Decided
- Before the lines we read: it was on an agenda to be extended or lifted, so it was in force then.
Every meeting it was on
Newest first: one agenda line a meeting, with the words that show it.
- Oct 27, 2026Extension proposed · Board of Commissioners Agendas and Minutes
“Consider Approval of 90-Day Extension of Data Center Moratorium”
- Jul 28, 2026Extension proposed · Board of Commissioners Agendas and Minutes
“Extending the Data Center Moratorium for an Additional Ninety (90) Days”
- Feb 24, 2026Proposed · Board of Commissioners Agendas and Minutes
“Consideration of Resolution Establishing a Temporary Moratorium on New Data Center Development”
The status comes from these lines: the AI says what each one did, and a vote the minutes record as passed counts as done. We may not yet have read every meeting. All meetings of Meriwether County.