Data center moratorium
City of Independence, MO
- Status
- In force Adopted
- Pauses
- Data centers
- Seen
- 3 meetings, Jun 22, 2026 to Jul 16, 2026
- Decided
- Jul 6, 2026
- Ends
- Jan 5, 2027
Every meeting it was on
Newest first: one agenda line a meeting, with the words that show it.
- Jul 16, 2026Discussion · Public Utility Advisory Board
“Update: Data Centers/Battery Sites — Pending Centers & Moratorium”
- Jul 6, 2026Adopted · Council Meetings
“declaring a 180-day moratorium on the processing of applications related to and issuance of city permits or licenses related to the installation or use of data processing and hosting facilities”
- Jun 22, 2026Proposed · Workshops & Study Sessions
“declaring a 180-day moratorium on the processing of applications related to and issuance of city permits or licenses related to the installation or use of data processing and hosting facilities”
The status comes from these lines: the AI says what each one did, and a vote the minutes record as passed counts as done. We may not yet have read every meeting. All meetings of City of Independence.