Data center moratorium

Gordon County, GA

Status
In force Adopted
Pauses
Data centers
Seen
4 meetings, Feb 3, 2026 to Jul 7, 2026
Decided
Before the lines we read: it was on an agenda to be extended or lifted, so it was in force then.

Every meeting it was on

Newest first: one agenda line a meeting, with the words that show it.

  1. Jul 7, 2026
    Extension proposed · Board of Commissioners

    “adopt resolution extending a temporary moratorium relating to Anaerobic Digestion Facilities and to adopt resolution extending a temporary moratorium relating to Data Centers”

    The agenda line · the meeting

  2. May 19, 2026
    Extension proposed · Board of Commissioners

    “adopt resolution extending a temporary moratorium relating to Data Centers”

    The agenda line · the meeting

  3. Mar 17, 2026
    Extension proposed · Board of Commissioners

    “extend Resolution Imposing a Temporary Moratorium relating to Data Centers for a ninety (90) day period”

    The agenda line · the meeting

  4. Feb 3, 2026
    Proposed · Board of Commissioners

    “Resolution Imposing a Temporary Moratorium relating to Data Centers for a sixty (60) day period”

    The agenda line · the meeting