Watches › Moratorium Watch › Data centers › Village of Cottage Grove
Data center moratorium
Village of Cottage Grove, WI
- Status
- Proposed On an agenda; no adoption read yet
- Pauses
- Data centers
- Seen
- 3 meetings, May 18, 2026 to Jul 20, 2026
Every meeting it was on
Newest first: one agenda line a meeting, with the words that show it.
- Jul 20, 2026Discussion · Village Board
“Discuss And Consider A Proposed Moratorium On Data Center Development In The Village Of Cottage Grove.”
- Jul 15, 2026Discussion · Plan Commission
“PUBLIC HEARING: The Public’s Opportunity To Provide Input Regarding A Proposed 18- Month Moratorium On Data Center Development In The Village Of Cottage Grove.”
- May 18, 2026Discussion · Village Board
“Discuss And Consider Staff Direction Regarding Possible Data Center Moratorium.”
The status comes from these lines: the AI says what each one did, and a vote the minutes record as passed counts as done. We may not yet have read every meeting. All meetings of Village of Cottage Grove.