- Decided
- Before the lines we read: it was on an agenda to be extended or lifted, so it was in force then.
Every meeting it was on
Newest first: one agenda line a meeting, with the words that show it.
- Aug 4, 2026Extension proposed · COMMISSIONERS 1ST TUESDAY
“DATA CENTER MORATORIUM EXTENSION”
- Jul 15, 2026Extension proposed · Planning Commission second Tuesday
“Six-month extension on the six-month Data Center Moratorium”
- Jun 16, 2026Discussion · COMMISSIONERS 3RD TUESDAY
“CONSIDERATION OF DATA CENTER MORATORIUM”
- Jun 9, 2026Proposed · Planning Commission second Tuesday
“Six-month Data Center Moratorium”
The status comes from these lines: the AI says what each one did, and a vote the minutes record as passed counts as done. We may not yet have read every meeting. All meetings of Madison County.