Watches › Moratorium Watch › Data centers › City of North Port
Data center moratorium
City of North Port, FL
- Status
- In force Adopted
- Pauses
- Data centers
- Seen
- 4 meetings, Jul 21, 2026 to Sep 22, 2026
- Decided
- Sep 22, 2026
Every meeting it was on
Newest first: one agenda line a meeting, with the words that show it.
- Sep 22, 2026Adopted · City Commission Regular Meeting
“Establishing a Temporary Moratorium on the Acceptance, Processing, Review, Approval, or Issuance of Building Permits”
- Aug 31, 2026Adopted · City Commission Special Meeting
“Establishing a Temporary Moratorium on the Acceptance, Processing, Review, Approval, or Issuance of Building Permits”
- Jul 29, 2026Discussed · City Commission Special Meeting
“Directing the City Manager to Schedule a Special Meeting in August to Act on the Ordinance Adopting a Moratorium on Data Centers”
- Jul 21, 2026Discussed · City Commission Regular Meeting
“Discussion and Possible Action Regarding Data Center Moratorium.”