Watches › Moratorium Watch › Data centers › City of Richmond
Data center moratorium
City of Richmond, CA
- Status
- In force Adopted
- Pauses
- Data centers
- Seen
- 3 meetings, Apr 21, 2026 to Oct 20, 2026
- Decided
- Before the lines we read: it was on an agenda to be extended or lifted, so it was in force then.
- Ends
- Sep 15, 2028
Every meeting it was on
Newest first: one agenda line a meeting, with the words that show it.
- Oct 20, 2026Extension proposed · City Council
“extending the temporary moratorium on the issuance of any new permit or land use approval for any data center in the City of Richmond for an additional 22 months and 15 days, until September 15, 2028”
- Sep 15, 2026Proposed · City Council
“establishing a 45-day temporary moratorium on the establishment of new data centers”
- Apr 21, 2026Discussion · City Council
“DIRECT the city manager and city attorney to work with Planning staff to develop and bring forward a proposed moratorium on data centers”
The status comes from these lines: the AI says what each one did, and a vote the minutes record as passed counts as done. We may not yet have read every meeting. All meetings of City of Richmond.