Watches › Moratorium Watch › Data centers › City of Arcata
Data center moratorium
City of Arcata, CA
- Status
- In force Adopted
- Pauses
- Data centers
- Seen
- 3 meetings, Sep 16, 2026 to Oct 28, 2026
- Decided
- Before the lines we read: it was on an agenda to be extended or lifted, so it was in force then.
Every meeting it was on
Newest first: one agenda line a meeting, with the words that show it.
- Oct 28, 2026Extension proposed · City Council - Special Meeting
“Extending Interim Urgency Ordinance No. 1594, Which Imposed a Temporary Moratorium on the Processing and Approval of New, Data Center Land Use Applications, for an Additional 10 Months and 15 Days”
- Oct 21, 2026On the agenda · City Council - Regular Meeting
“Imposing a 45-Day Moratorium on Processing Data Center Land Use Applications”
- Sep 16, 2026Proposed · City Council - Regular Meeting
“Imposing a 45-Day Temporary Moratorium on the Processing and Approval of New Land Use Applications for Data Centers”
The status comes from these lines: the AI says what each one did, and a vote the minutes record as passed counts as done. We may not yet have read every meeting. All meetings of City of Arcata.