Data center moratorium

Camden County, GA

Status
In force Adopted
Pauses
Data centers
Seen
3 meetings, Apr 7, 2026 to Nov 3, 2026
Decided
Before the lines we read: it was on an agenda to be extended or lifted, so it was in force then.

Every meeting it was on

Newest first: one agenda line a meeting, with the words that show it.

  1. Nov 3, 2026
    Extension proposed · Board of County Commissioners

    “Extension of Temporary Moratorium on Data Centers.”

    The agenda line · the meeting

  2. May 5, 2026
    Proposed · Board of County Commissioners

    “Establishing a Temporary Moratorium on the Acceptance, Review, and Approval of Applications for Data Centers”

    The agenda line · the meeting

  3. Apr 7, 2026
    Proposed · Board of County Commissioners

    “Establishing a Temporary Moratorium on the Acceptance, Review, and Approval of Applications for Data Centers”

    The agenda line · the meeting

The status comes from these lines: the AI says what each one did, and a vote the minutes record as passed counts as done. We may not yet have read every meeting. All meetings of Camden County.