Crypto mining moratoriums
Where they stand
Every record
Votes ahead first, then the newest agenda.
- Nov 18
“add a temporary moratorium regarding applications for data centers and digital mining uses”
- Nov 16Town of Cicero, NYIn force
“there will be a twelve (12) month moratorium on all Town Board land use decisions related to data centers, artificial intelligence computing facilities, cryptocurrency mining facilities, and/or high-intensity computing sites in Cicero.”
- Nov 16newPasquotank County, NCProposed
“public hearing on the proposed ordinance (attached) instituting a temporary moratorium on the permitting of data centers, data processing facilities, cryptocurrency mining operations”
- Nov 5Town of Butner, NCIn force
“Extending the Temporary Moratorium on the Acceptance, Processing, and Approval of Development Approvals for Data Centers, Data Processing Facilities, Cryptocurrency Mining Facilities”
- Nov 2City of Dickson, TNIn force
“Ordinance #1591: An Ordinance to Amend Ordinance #1585 to Extend the Temporary Six (6) Month Moratorium on the Acceptance, Processing, and Approval of Applications for Permits”
- Oct 27Morton County, NDIn force
“Second reading of Resolution 30-2026-02 to lift the moratorium on data centers and cryptocurrency mining facilities.”
- Oct 21Town of Marcellus, NYProposed
“Twelve (12) Month Moratorium on Commercial Cryptocurrency Mining Operations, Data Mining, Data Processing Centers, and Data Storage Facilities”
- Oct 21Town of Awendaw, SCProposed
“Ordinance 2026-34: An ordinance declaring a Temporary Moratorium on the acceptance of, review of, and/or action upon applications”
- Oct 20Town of Bergen, NYIn force
“will not complete the plan prior to the expiration of the moratorium”
- Oct 7Township of Joyfield, MIProposed
“Data Center & Cryptocurrency Mining Facilities Moratorium”
- Sep 29City of Buffalo, NYProposed
“Resolution to Adopt a Two-Year Moratorium on Cryptocurrency Mining and Data Processing Centers”
- Sep 28City of Keene, NHProposed
“written findings from the Planning Board to support a temporary moratorium on data centers and cryptocurrency mining facilities”
- Sep 24Town of Frankfort, NYProposed
“Moratorium on commercial cryptocurrency mining operations and data processing centers”
- Sep 22Kershaw County, SCProposed
“An Ordinance Establishing A Temporary Moratorium On The Acceptance Of, Review Of, And/Or Action Upon Applications For Zoning Approvals”
- Sep 21Benton County, TNProposed
“ESTABLISHING A TEMPORARY MORATORIUM ON CERTAIN COUNTY ACTIONS FACILITATING THE ESTABLISHMENT, CONSTRUCTION, DEVELOPMENT, EXPANSION, OR OPERATION OF DATA CENTERS, CRYPTOCURRENCY MINING FACILITIES”
- Sep 21City of Trinity, NCProposed
“Ordinance Instituting a Temporary Moratorium on the Permitting of Data Centers, Data Processing Facilities, Cryptocurrence Mining Operations”
- Sep 21Nash County, NCIn force
“Temporary Development Moratorium on data centers, data processing facilities, cryptocurrency mining operations”
- Sep 15Marion County, FLIn force
“Impose a Temporary Moratorium on Acceptance, Review, or Approval of Applications for Development Permits, Development Orders, Rezoning, or Site Plans Related to Data Centers”
- Sep 15Louisa County, IAProposed
“second reading with possibility of waiving of third reading of Ordinance 26- 2 Moratorium on Cryptocurrency Mining”
- Sep 14City of Chatsworth, GAProposed
“establish a temporary moratorium on the acceptance, review, processing, and approval of applications for data centers, cryptocurrency mining facilities”
- Sep 10Town of Newport, NCProposed
“CONSIDER A PUBLIC HEARING FOR A REQUEST TO ENACT A 1-YEAR MORATORIUM ON THE PERMITTING OF DATA CENTERS”
- Sep 8City of Foley, ALIn force
“IMPOSING A TEMPORARY MORATORIUM ON THE ACCEPTANCE, PROCESSING, APPROVAL, AND CONSIDERATION OF APPLICATIONS FOR DATA CENTERS, BITCOIN AND CRYPTOCURRENCY MINING FACILITIES”
- Sep 8Jasper County, SCProposed
“Declaring a Temporary Moratorium on the Acceptance of, Review of, and/or Action Upon Applications for Rezoning”
- Sep 8Orangeburg County, SCProposed
“An Ordinance Declaring a Temporary Moratorium on the Acceptance of, Review of, and/or Action Upon Applications for Rezoning, Special Exceptions”
- Sep 2Village of Newton Falls, OHProposed
“TEMPORARY TWELVE (12) MONTH MORATORIUM ON THE ESTABLISHMENT, EXPANSION, OR DEVELOPMENT OF DATA CENTERS”
- Sep 1Fulton County, ILIn force
“Six (6) Month Extension for Previously Passed “Ordinance Establishing a Temporary Moratorium on Data Center & Commercial Crypto Mining Operations Applications for Development in Fulton County””
- Aug 25City of Whiteville, NCProposed
“10.1 Discussion & Decision-Ordinance#2026-O-103 Temporary Moratorium on Development Approvals for Data Centers, Data Processing Centers, and Crypto Currency Mining Operations”
- Aug 17City of Kalamazoo, MIProposed
“Resolution Establishing a Moratorium on the acceptance and/or processing of applications for Data Centers, Battery Energy Storage Systems, Cryptocurrency Mining Centers”
- Aug 17Township of Genoa, MIIn force
“extend the temporary Moratorium on the Acceptance and Approval of Applications for Data Centers and Cryptocurrency Mining Facilities”
- Aug 6Town of Hilliard, FLProposed
“Town Council to consider adopting Ordinance No. 2026-05, on Second & Final Reading.”
- Aug 5Leavenworth County, KSProposed
“providing for a moratorium on applications for cryptocurrency mining operations”
- Aug 3Camden County, NCProposed
“a proposed temporary one (1) year moratorium on the acceptance and processing of applications for the development, construc”
- Aug 3City of Edgewater, FLIn force
“Permanent Moratorium on the Acceptance, Processing, Review, Approval, and Issuance of Development Orders”
- Jul 22Town of Nashville, NCProposed
“moratorium on the development of Data Centers, Data Processing Facilities, and Cryptocurrency Mining in Nashville”
- Jul 21City of Lincolnton, NCProposed
“imposing a one-year moratorium on the acceptance, processing, and approval of applications for data centers, data processing facilities, cryptocurrency mining operations”
- Jul 16Town of Caroline, NYProposed
“…own Hall by Zoom videoconference following the Public Hearing on a local law to effect a moratorium on cryptocurrency mining operations and large data centers. Members of the public may attend in-person or by Zoom. Min…”
- Jul 8City of Loudon, TNProposed
“temporary moratorium on Data Center approvals, permits, and operations (including data mining, processing, and AI activities)”
- Jul 8Town of Hartland, NYProposed
“Data Center and Bitcoin Moratorium Law of the Town of Hartland.”
- Jul 8Town of Scipio, NYIn force
“A Local Law Imposing a Twelve (12) Month Moratorium on the Development or Construction of Data Centers, Accessory Data Centers and Cryptocurrency Data Mines”
- Jun 30City of Shelbyville, TNProposed
“Approving and Authorizing a Moratorium on Development of all Data Centers, Including Cryptocurrency Mining”