- A)August 11, 2026 Minutes p. 1
- A)E-Bike Ord. - Next Steps - The E-Bike ordinance passed both first & second readings of the ordinance. What are the next steps to execute the ordinance?
- B)4 way stop - Indian Bayou/Country Club Dr East. - Delay posting of 4 way stop. Relook/local study of the Indian Bayou entrance (4 way stop). City Council on 8 Sept asked for at least a local study of some kind.
- C)Beach and Benning School Zone - Per Chair email - Beach and Benning School related issues previously voted on: Please coordinate with Principal Amy Morgan for concurrence before we execute. I want the local principal involved. At a minimum, provide an understanding of why we want to make the changes. If I was not out of town, I would get to it and still might this week. If I do, I will let you know. • Adding flashing yellow light and school zone signs on Benning • Moving flashing yellow light and school zone signs on Beach 50 feet to the south
- D)Curbing at Spring Lake and Kelly - Per Chair email - Small piece of curbing (Spring Lake and Kelly) from the recent resurfacing. Curbing was broke, I thought you said they knew and would fix. Checked yesterday, not fixed.
- E)Destin Cross-Town Connector Barrier & Update - Providing information per the request of the Committee Chair.
- F)Rapid Flashing Beacons New Locations - The FY27 year has started and the Committee has $100,000 for public safety improvements contingent upon City Council approval. New rapid flashing beacon locations would be discussed in this agenda.
- G)Vera Cruz, Osceola and Durango (city portion) - Will Vera Cruz, Osceola and Durango (city portion) roads be repaved, and if so, when? Yes, Vera Cruz 2027, Osceola 2028 and Durango (city portion) 2031.
- H)Utility Undergrounding Schedule - The city is currently working through Phase 1 of the citywide undergrounding project. Phase 1 is the only one authorized by council. The current phase is in the switching and wreck-out stages. Completely dependent on FPL’s schedule. Could easily take 6 months or more. There is no schedule for any other phases at this time. The phasing is ordered 1 through 7, and the council has voted that it will follow that order. We have not received approval to begin any activities to move Phase 2 forward.
- I)Sidewalk on Durango Rd p. 1
- J)R & R - Road Resurfacing 2027 - City Council has approved an aggressive resurfacing schedule for the public roadways within the city to ensure the streets are updated and maintained to a minimum for road surfacing standards. Attached are quotes for the following groups (1 through 8 and 10) of roadways to be resurfaced in FY 2027. The quote is the standard 2” mill & 2” resurface (SP-9.5 with fiber) for each group. The milling and resurfacing of each group will be completed in rapid succession from beginning of milling to the end of paving. Staff will be looking to get started by Mid-Oct 2026. Group 1 Ann Cir Indian Oaks Dr Legion Ct Cardinal Ln Seagull Ln Spring Ln Swan Ln Whippoorwill Ln Group 2 Kell-Aire Ct Kell-Aire Dr Juniper Ct Juniper St Cypress St Cedar St Wild Oak Ave Group 3 Sea Oats Dr Sea View Cir Sea View Dr Group 4 Fleshman Dr Juanita Ave Maltezos St Stahlman Ave (Benning to …
- K)3784 Misty Way No Parking Sign Request - Staff has received a request for no parking signs on the subject property of the Misty Ct entry. The request has gone to engineering in accordance with ADM 94 to provide an opinion. Upon initial review, the requested area of Misty Ct is near the intersection with Misty Way. There are no driveways on this stretch of roadway and the right of way. There has been parking on the right-of-way observed. Vehicles parking on the ROW have killed the grass and broken the sprinkler heads on the frontage.
- L)Clipper Cove Entry No Parking Request - Staff has received a request for no parking signs on both sides of the Clipper Cove entrance. The request has gone to engineering in accordance with ADM 94 to provide an opinion. Upon initial review, the requested area of Clipper Cove is the entry road for the entire subdivision. There are no driveways on this stretch of roadway and the right of way contains street trees, which do not allow for right of way parking off the street. Three of the four houses fronting this segment of roadway appear to be short-term rentals. There has been parking on the street, on both sides of the street observed. Vehicles parking on the street reduces safe access to the subdivision.
- A)Chairman Wood
- B)Vice Chair Green
- C)Committee member Tom Weidenhamer p. 1
- D)Committee member Smith p. 1
- E)Committee member Tammy Weidenhamer p. 1
- F)Committee member Ansley p. 2
- G)Committee member Bell p. 2