City of Tuscaloosa, AL · pop. 101K
Tue17Nov2:30 PM
Public Projects Committee
Tue Nov 17, 2:30 PM · Council Chamber · 5 days ago
Agendatuscaloosaal.api.civicclerk.com
Minutesnot posted yet
Meeting page ↗tuscaloosaal.portal.civicclerk.comThis agenda in plain words
Leer en españolThis is a regular meeting of the City of Tuscaloosa's Public Projects Committee on Tuesday, November 17, 2026, at 2:30 p.m. in the Daugherty Conference Room. Most items are requests to approve contracts with companies for water, sewer, road, and building work, and the committee will decide on each one.
- Decide whether to award a construction contract to rebuild valves at Lift Stations 39, 15, and 42. The work replaces 24 valves so pumps can be serviced. It should take about 45 days. $503,004.00. Touches: Water and sewer customers served by Lift Stations 39, 15, and 42. p. 3
- Decide whether to approve a request to modify facilities at the 29th Street Water Tank site so T-Mobile South, LLC can upgrade its equipment. Touches: T-Mobile South, LLC, and the 29th Street Water Tank site. p. 1
- Decide whether to approve an engineering contract with Krebs Engineering to design and oversee repairs to the Hillcrest 1.5 million gallon water storage tank. Repairs include blasting, epoxy and coating, and a new logo. Design takes about 90 days and construction about 150 days. $71,805. Touches: Water customers served by the Hillcrest water tank. p. 4
- Decide whether to approve an engineering contract with Jacobs Engineering to inventory and assess the booster pump stations and produce a plan for future repairs and upgrades, with 5-year and 10-year projections. It should take 6 months. $124,950. Touches: Tuscaloosa water customers and the booster pump stations. p. 5
- Decide whether to approve a contract with Thompson Engineering to study why the road settled on Jack Warner Parkway East of Greensboro Avenue. The work includes soil borings, weekly groundwater checks, lab tests, and a report. The contract lasts one year. $49,750.00 maximum. Touches: Drivers and residents near Jack Warner Parkway East of Greensboro Avenue. p. 6
- Decide whether to approve a contract with Central Alabama Asphalt & Construction Co. to patch roads and parking areas as needed, citywide. These patches are bigger than routine crew repairs but do not need full resurfacing. $99,825.00. Touches: Drivers and residents citywide; roads and right-of-way parking areas. p. 7
- Decide whether to approve a contract with Amason & Associates, Inc. to renovate the Tuscaloosa Police Department gym. $87,702.00. Touches: Tuscaloosa Police Department. p. 8
- Decide whether to approve a contract with Building Specialties Co. to repair door closers in City Hall Annex 3. $7,251.00. Touches: City Hall Annex 3 staff and visitors. p. 9
- Decide whether to award the bid and sign a contract with McKelvey Mechanical, Inc. to replace the heating and cooling system at the Jerry Plott Water Treatment Plant. McKelvey had the lowest bid. $1,254,155.00. Touches: Water treatment plant at Jerry Plott. p. 10
Words on this agenda, explained
- Minor public works contract
- A contract for smaller city construction or repair jobs, signed without the full bidding process used for large jobs.
- Professional services agreement
- A contract to hire an outside firm for expert work such as design, studies, or planning, rather than construction.
- Award
- The city chooses which company gets the job, usually the one with the lowest bid.
- UST Closure Assessment Report Form
- A state form about closing out an underground storage tank, which the agenda asks the committee to let the city sign.
- Lift station
- A small pumping station that moves sewage up a hill or through pipes so it can flow onward.
- Asset management plan
- A written plan that lists the city's equipment, checks its condition, and sets out what to fix or replace and when.
Written by AI from the agenda, Nov 14. Each point links to its page: read it there before you rely on it. Nothing here says how the board will vote.
1 item on this agenda matches the land-use topicsInfrastructure (1)
Agenda items (13)Show only the 1 matching
- 1. Approval of awarding contract to Mark Johnson Construction, LLC for the Lift Station 39, 15, and 42 Valve Replacements project (OCA-26-1176) p. 1
- 3. Approval of a professional services agreement with Krebs Engineering for the Hillcrest Tank Rehabilitation project (OCA-26-1541) p. 1
- 4. Approval of a professional services agreement with Jacobs Engineering for the Booster Pump Stations Asset Management Plan (OCA-26-1540) p. 1
- 5. Approval of a professional services agreement with Thompson Engineering for engineering services for the evaluation of the settlement on Jack Warner Parkway East of Greensboro Avenue (OCA-26-1535) p. 1
- 6. Approval of a minor public works contract with Central Alabama Asphalt & Construction Co. for as-needed patching (OCA-26-1534) p. 1
- …ft Station 39, 15, and 42 Valve Replacements OCA-26-1176 Engineering Project No. 2026.737.001 Request: The Water and Sewer Department is recommending award of contract in the amount of $503,004.00 to Mark Johnson Construction, LLC. Project Description: This project is to replace multiple valves (24 total) within Lift Stations 39, 15, and 42. Lift Stations 39 and 42 has three pumps and Lift Station 15 has two pumps. At each pump, there is a suction side isolation valve, discharge side isolation valve, and a check valve. Each of these valves needs replacement to allow pump service and maintenanc… p. 3
- …randum To: Public Projects Committee From: Kris Harbin Water & Sewer Department Date: November 6, 2026 Re: 2026.703.002 Hillcrest Tank Rehabilitation Professional Services Agreement Request: Reques-ng authoriza-on of a professional services agreement with Krebs Engineering in the amount of $71,805. Project Descrip-on: The contract scope includes design, bid-phase, and construc-on administra-on services for rehabilita-ng the Hillcrest 1.5 million gallon elevated water storage tank. The scope of rehabilita-on work includes blas-ng interior wet surfaces and applying water-safe epoxy; blas-ng the… p. 4
- …$124,950. Project Descrip-on: The contract scope includes asset inventory, condi-on assessment, and risk management, and culminates in a recommended capital improvement plan for Tuscaloosa Water booster pump sta-ons, including: 5-year and 10-year capital planning projec-ons and a priori-zed list of projects. Project Schedule: The professional services should take 6 months to complete. Project Funding: This project is funded by 2022B bond 62240280-24527. 5 p. 5
- …LS City Engineer RE: Evaluation of Jack Warner Parkway Settlement OCE Project No. 2026.056.001 Request: The Office of the City Engineer is requesting approval of a contract with Thompson Engineering to provide professional engineering services for the evaluation of the settlement on Jack Warner Parkway East of Greensboro Ave. This contract will be for a maximum of $49,750.00 for a one-year period. Contract Scope: The services to be performed but not limited to: - Perform Standard Penetration Test (SPT) borings - Monitor groundwater weekly - Conduct laboratory tests on soil samples - Prepare ge… p. 6
- Memorandum November 5, 2026 To: Public Projects Committee From: Laine McCool Project Manager RE: As-needed Patching OCE Project No. 2026.055.001 Approval of Minor Public Works Contract Request: The Office of City Engineer (OCE) is recommending approval of a minor public works contract with Central Alabama Asphalt & Construction Co. for As-needed Patching in the amount of $99,825.00. Project Description: Certain roads and ROW parking areas require substantial patching, but their overall road condition does not justify resurfacing. This project addresses repairs that are larger in scope than the… p. 7
- Memorandum November 17, 2026 To: Public Projects Committee From: Jamie Roberts Construction, Facilities, and Grounds RE: Authorization enter into a Minor Public Works Contract with Amason & Associates, Inc., in the amount of $87,702.00. General Information: Company: Amason & Associates, Inc. Funding: 10709042-24516 Amount: $ 87,702.00 Summary: Requesting authorization to enter a Minor Public Works Contract with Amason & Associates, Inc., in the amount of $87,702.00. The scope of this contract is to renovate Tuscaloosa Police Department gym. 8 p. 8
- Memorandum November 17, 2026 To: Public Projects Committee From: Jamie Roberts Construction, Facilities, and Grounds RE: Authorization enter into a Minor Public Works Contract with Building Specialties Co., in the amount of $7,251.00. General Information: Company: Building Specialties, Co. Funding: 10109042-3100 Amount: $ 7,251.00 Summary: Requesting authorization to enter a Minor Public Works Contract with Building Specialties Co., in the amount of $7,251.00. The scope of this contract is to repair door closers in City Hall Annex 3. 9 p. 9
- Memorandum November 17, 2026 To: Public Projects Committee From: Jamie Roberts Construction, Facilities, and Grounds RE: Jerry Plott Water Treatment HVAC Project - Authorization to award bid to McKelvey Mechanical, Inc., in the amount of $1,254,155.00. General Information: Company: McKelvey Mechanical, Inc. Funding: 62240310-26537 Amount: $ 1,254,155.00 Summary: Requesting authorization to award bid to and enter into a public works contract with McKelvey Mechanical, Inc. for the Jerry Plott Water Treatment HVAC project for the base bid in the amount of $1,254,155.00. The scope includes replaci… p. 10