Columbia County, GA · pop. 160K
Tue22Sep8:30 AM
Public Works Services
Tue Sep 22, 8:30 AM · 2 months ago
Public Works and Engineer Services
Agendacolumbiacoga.api.civicclerk.comMinutescolumbiacoga.api.civicclerk.comRecording ▸YouTubeAttachment26-20 Initial Resolution Crawford Place Lane_TraAttachmentCrawford Place Lane_6_18_2026 - platAttachment26.21 Initial Resolution Crawford Place Lane_TraAttachmentCrawford Place Lane_6_18_2026 - platAttachment26-22 Initial Resolution Crawford Place Lane_TraAttachmentCrawford Place Lane_6_18_2026 - platMeeting page ↗columbiacoga.portal.civicclerk.com
5 items on this agenda match the land-use topicsSubdivisions (3), Infrastructure (2)
Agenda items (23)Show only the 5 matching
- 1.August 25, 2026
- 1.New Business
- a.Deputy County Manager p. 1
- 1.Purchase from Blanchard Equipment for 5105M Tractor and Single Wing Mower Attachment - Fleet Services obtained quotes from Blanchard Equipment for three John Deere 5105M Tractors and a John Deere Single Wing Mower Attachment. The pricing provided by Blanchard Equipment is based on Georgia State Contract. The tractors and mower attachment will be purchased to replace aging equipment currently assigned to Roads and Bridges fleet. The existing units will then be surplused following the replacement. p. 1
- b.Engineering Services p. 1
- 1.Change Order #1 to Contract#2025-3123 with Goodwyn Mills Cawood for the Design of the Euchee Creek Greenway All Remaining Phases Project - Location – This project is to construct various sections of 10-ft wide shared-use path to complete several connections of the Euchee Creek Greenway trail system programmed in TIA2. The sections include: Along William Few Pkwy from the trailhead near Baker Place Landfill to the existing Patriots Park Trail near the intersection of William Few Pkwy and Columbia Road. Along William Few Pkwy from the existing Patriots Park Trail on the north side of the property to the future Riverwood Park near the intersection of Hardy McManus Rd and William Few Pkwy. Along the GA Power Easement from Blanchard Woods Park to the future Riverwood Park near the intersection of Hardy McManus Rd and William Few Parkway. Request – Approve Change Order #1 to… p. 1
- 2.Bid# 2026027-BID2710 and Contract #2026-3708 with Peek Pavement Marking, LLC for the 2026 SAP Striping and Signs Project - Location – Various County Roads (reference history below) Request – Approve Bid# 2026027-BID2710 and Contract# 2026-3708 with Peek Pavement Marking, LLC for the 2026 SAP Striping and Signs Project in the amount of $378,736.34. History – On 7/21/26, the Board of Commissioners approved the acceptance of the 2026 LMIG Safety Action Plan Grant. Staff advertised the project and bids were opened on August 20, 2026, with the lowest, most responsive bidder being Peek Pavement Marking, LLC. The project includes striping, raised pavement markers (RPM), and sign replacement installation: Louisville Rd, Old Washington Rd, and Dozier Rd to receive new striping, stop bars, RPMs, and signs. William Few Pkwy, Ray Owens Rd, and Harlem Grovetown Rd to receive new RPMs only. Traffic…
- 3.Change Order #1 to Contract #2025-3375 with UES Professional Solutions 18, LLC for Geotechnical Services on the Wrightsboro Rd Widening Project - Location - Wrightsboro Rd from Jimmie Dyess Pkwy to Horizon South Pkwy Request - Approve Change Order #1 to Contract# 2025-3375 with UES Professional Solutions 18, LLC for Geotechnical Services on the Wrightsboro Rd Widening Project in the amount of $373,765.89. History - In May 2025, the Board of Commissioners entered into contract with Alfred Benesch & Company (Benesch) to deliver the Preliminary Engineering (PE) phase of the Wrightsboro Rd Widening Project. Since the commencement of design, it was been determined that Geotechnical Services related to a Pavement Evaluation and a Limited Phase I Environmental Site Assement are required; however, these services are outside Benesch's contracted scope of work. In December of 2025, the Board of…
- 4.…intersection with Crawford Place Road continuing North for approximately 950 feet, shown more specifically on the attached plat dated 6/18/2026, and labeled “Tract 1 Local Road.” Request - Approve Resolution 26-20 to abandon and sell a portion of Crawford Place Lane. History – Purchased in 2009 to continue the access road behind North Columbia Elementary School. The elementary school has since been demolished and this section of road is no longer needed. Funding - No funding required. Timeline - With Commission's approval of the Resolution, there will be a two week advertising period followed by a public hearing at the next available Public Works and Engineering Service Committee meeting. At the following Commissioners' Meeting, a report of the public hearing will be presented with a second Resolution proposing to abandon the ROW and proceed to a sale according to the Georgia State Law. p. 1
- 5.…and Connecting both sections of “Tract 1 Local Road” and “Tract 3 Local Road” as shown more specifically on the attached plat dated 6/18/2026, and labeled “Tract 2 Local Road.” Request - Approve Resolution 26-21 to abandon and sell a portion of Crawford Place Lane. History – Purchased in 1988 to continue the access road behind North Columbia Elementary School. The elemen tary school has since been demolished and this section of road is no longer needed. Funding - No funding required. Timeline - With Commission's approval of the Resolution, there will be a two week advertising period followed by a public hearing at the next available Public Works and Engineering Service Committee meeting. At the following Commissioners' Meeting, a report of the public hearing will be presented with a second Resolution proposing to abandon the ROW and proceed to a sale according to the Georgia State Law. p. 2
- 6.…Owens Road continuing west down Crawford Place lane for approximately 1,050 feet, shown more specifically on the attached plat dated 6/18/2026, and labeled “Tract 3 Local Road." Request - Approve Resolution 26-22 to abandon and sell a portion of Crawford Place Lane. History – Purchased in 1988 to continue the access road behind North Columbia Elementary School. The elementary school has since been demolished and this section of road is no longer needed. Funding - No funding required. Timeline - With Commission's approval of the Resolution, there will be a two week advertising period followed by a public hearing at the next available Public Works and Engineering Service Committee meeting. At the following Commissioners' Meeting, a report of the public hearing will be presented with a second Resolution proposing to abandon the ROW and proceed to a sale according to the Georgia State Law. p. 2
- 7.Purchase from Environmental Products Group an Envirosight RovverX Pipeline Inspection Camera for the Stormwater Operations Department - Location - N/A Request - Purchase of an Envirosight RovverX Pipeline Inspection Camera for the Stormwater Operations Department in the amount of $129,700.00. History - The Stormwater Operations Department conducts inspections of newly installed underground storm sewer systems prior to the County accepting ownership, as well as inspections of 20% of the county's existing storm sewers every year as required by our MS4 Permit. The current camera (RapidView IBAK Inspection System) is over 10 years old, frequently malfunctions and needs repairs, and replacement parts are very limited. This downtime greatly reduces the inspection crew's production and efficiency. The purchase of the subject camera is to equip the inspection crew with more reliable equipment… p. 2
- 8.Change Order #1 to Contract # 2026-3567 with East Coast Grading, Inc. for LMIG 2026 - Location - McCrary Ct. and Claudia Dr. Request - Approve Change Order # 1 to Contract # 2026-3567 with East Coast Grading, Inc. for LMIG 2026 for an amount not to exceed $310,000.00. History - Through the LMIG and LRA Programs the County has been granted $11,022,758.34, including a 10% match from the County. As a condition of receiving the grants, all authorized funds must be spent in totality. Currently the County has a shortfall of obligated expenditures, detailed as follows: Total Funds Authorized through the LMIG and LRA Programs: $11,022,758.34 Total Funds Obligated through Contracts and Change Orders To Date: $10,687,424.58 Balance of Unobligated Funds that must be spent: $335,333.76 East Coast Grading, Inc. is currently under contract to complete work submitted for the LMIG 2026 program. County… p. 2
- c.Other Committees
- 2.Items Added at the Meeting p. 2
- 1.Water Utility
- a.Year to Date Budget Report p. 2
- b.Water and Sewer Construction Projects Report p. 2
- 2.Engineering Services p. 1
- a.Roadway Projects Report p. 2
- b.Roadway Resurfacing Report p. 2
- 1.Property A - Project PI# 0012865 Hereford Farm Road Widening Project During the condemnation process a settlement was reached during mediation. Closing will proceed as normal. An independent appraisal was submitted and approved by the GDOT Review Appraiser. Parcel Name FMV / Cost to Cure Total 182 Matthew M. George Tax Parcel # 072A001C Parcel 182: 0.004 AC (Fee); 0.039 AC (Perm); Appraised FMV: $22,300.00 Amount previously approved: Court Deposit: $22,300.00 Settlement: $10,600.00 Total Amount: $32,900.00 $10,600.00 Grand Total $10,600.00
- 2.Property B - TIA Project PI# 0008351 Horizon South Parkway Road Widening Project During construction, a field change that required relocating a water line necessitated the need to acquire this permanent easement. Staff has negotiated with the following property owners to obtain the permanent easement for the Horizon South Parkway Road Widening Project. All negotiations were performed in accordance with the Uniform Act, a Code of Federal Regulations, and approved by the GDOT TIA Right of Way Manager. An independent appraisal was submitted and approved by the TIA Right of Way Manager. Parcel Name FMV / Cost to Cure Total 27A Deere & Company Tax Parcel # 069 983B Parcel 27A: 0.016 (PermEase) Original Offer: $700.00 $700.00 Grand Total $700.00