- 1.Approval of Board of Public Works Minutes for the week of November 3, 2026. p. 1
- 2.Approval of Public Hearing Minutes for the week of November 3, 2026.
- 3.Approval of Resolution #1122N, Vesey Ave Street Lighting Improvements. p. 1
- 4.Approval of Resolution #113-11-10-26-2, Confirming Condemnation and Awarding Damages for Easement Acquisitions for Tamarack Neighborhood Storm Improvements Phase 1. p. 1
- 5.Approval of Professional Services Agreement between the City of Fort Wayne and Dixon Engineering for WO #67331, Coldwater Tank Painting. Compensation for services performed shall not exceed $58,000.00. p. 1
- 6.Approval of Professional Services Agreements for Relocation Services with Dena's Place Real Estate Services and Boomerang Ventures. Compensation for services performed shall not exceed $50,000 per year per firm. p. 1
- 7.Approval of Professional Services Agreement between the City of Fort Wayne and EcoEngineers for WO #77202, Renewable Natural Gas Renewable Fuel Standard Support. Compensation for services performed shall not exceed $96,000.00. p. 1
- 8.Approval of Amendment #1 to Professional Services Agreement between the City of Fort Wayne and Phoenix Consulting for WO#67290, Three Rivers Filtration Plant SCADA Migration Work Package #1. Compensation for services performed shall be increased by $49,055.00, bringing the total fee to $480,810.00, and extends the completion date to June 30, 2027. p. 1
- 9.Approval of Change Order #1 & Final between the City of Fort Wayne and Key Concrete for Contract #0857C, Kirkwood Park Concrete Street Repairs. This change order increases the original contract price by $45,928.42 to a final contract price of $2,218,498.42. p. 1
- 10.Approval of Change Order #1 & Final between the City of Fort Wayne and Milestone Contractors for Contract #0915A, West Cook Rd Concrete Repairs. This change order increases the original contract price by $7,463.14 to a final contract price of $1,887,314.87. p. 1
- 11.Approval of Change Order #1 & Final between the City of Fort Wayne and Kissinger Electric for Contract #1008L, Burgess St and Saint Mary's Ave Street Lighting Improvements. This change order decreases the original contract price by $9,950.00 to a final contract price of $146,615.00 and extends the completion date by 63 days. p. 1
- 12.Approval of Change Order #1 & Final between the City of Fort Wayne and Kissinger Electric for contract #1011L, Francis Street Lighting Improvements from East Berry St to East Lewis St. This change order decreases the original contract price by $18,600.00 to a final contract price of $95,490.00 and extends the completion date by 36 days. p. 1
- 13.Approval of Change Order #1 & Final between the City of Fort Wayne and Upper Cumberland Utility Solutions for Contract #1030L, East Lewis Street Lighting Improvements from Harmar St to South Anthony Blvd. This change order decreases the original contract price by $71,118.36 to a final contract price of $162,072.08 and extends the completion date by 81 days. p. 1
- 14.Approval of recommendation from Transportation Engineering to award #0792D, Alley North/South: Lenox Ave, West Fairfax Ave, Buell Dr and Fairfield Ave to Vino Concrete in the amount of $133,586.25. p. 2
- 15.Approval of recommendation from City Utilities to award #67616, Tract 11 Lead Service Line and Water Main Replacement to Underground Contractors in the amount of $4,730,690.00. p. 2
- 16.Approval of Change Order #1 & Final between the City of Fort Wayne and Shannon Concrete for Contract #0764D, Alley East/West: Rivermet Ave, Lake Ave, Tecumseh St and Oneida St. This change order decreases the original contract price by $4,536.00 to a final contract price of $76,097.00. p. 1
- 17.Approval of Change Order #1 & Final between the City of Fort Wayne and Kissinger Electric for Contract #1091L, 700-900 Block Saint Mary's Street Lighting Improvements. This change order decreases the original contract price by $8,000.00 to a final contract price of $49,270.00. p. 1
- 18.Acceptance of the work performed by Thieneman Construction for #77084, South Foster Park Wet Weather Pump Station as an integral part of the City's sanitary sewer system.
- 19.Approval of Full Release of Escrow with Centier Bank from Thieneman Construction for Resolution #77084, South Foster Park Wet Weather Pump Station. p. 2
- 20.Approval of Civil City Payroll Claims in the net amount of $4,072,170.17 for the pay period ending October 31, 2026. p. 2
- 21.Approval of City Utilities Payroll Claims in the net amount of $898,635.69 for the pay period ending October 31, 2026. p. 2
- 22.Approval of Civil City Accounting Claims in the amount of $6,206,310.48 for the week of November 4, 2026. p. 2
- 23.Approval of City Utilities Accounting Claims in the amount of $4,799,207.78 for the week of November 10, 2026. p. 2