Leer en españolThis is a regular meeting of the Porter County Storm Water Management Board on November 17, 2026, at 9:00 am. The main items are two change orders on storm drain construction contracts, which adjust the price or the finish dates of the work.
- Final change order on the North Stimson Drain Reconstruction contract with Austgen Equipment. It adjusts the price to match final measured work and moves the final finish date from December 31, 2025 to October 15, 2026. p. 1
- Final change order on the Olney Road Storm Sewer Reconstruction contract with Grimmer Construction Inc. It moves the final completion date from July 31, 2026 to November 17, 2026. p. 1
Words on this agenda, explained
- Change order
- A written change to a construction contract that alters the price or the finish date of the work.
- Drain
- A ditch or pipe that carries storm water away from an area.
Written by AI from the agenda, Nov 14. Each point links to its page: read it there before you rely on it. Nothing here says how the board will vote.
Agenda items (1)
- …al measured quantities of the various items of work involved and to extend the final completion date from December 31, 2025 to October 15, 2026. Such change order will decrease the value of the contract by $36,462.00 to a total contract price of $1,694,429.70. #P25-005 Olney Road Storm Sewer Reconstruction (Grimmer Construction Inc.) – Change Order #4 (FINAL) to extend final completion date from July 31, 2026 to November 17, 2026. o Storm Water Program Manager Report o Bridge Report • Any Other Matters Which May Properly Come Before the Board • Next Meeting o December 8, 2026, 9:00 am • Rece… p. 1