This is a regular, virtual meeting of the Ad-Hoc Windham High School Renovate as New Building Committee, held by video call under a state law that allows remote meetings. The main items are progress reports on the high school project, requests for extra work and payment from several firms, and a credit from the construction contractor.

  1. Requests for extra work from GM2 (formerly RZ) and Friar for system commissioning, not to exceed $6,360.00. $6,360.00. p. 1
  2. A request for extra work from Martinez Couch Associates on the formal completion of the close-out paperwork and the construction contract, as a lump sum. $17,637.00. p. 1
  3. A vote on Downes change order PCO #827, a credit that reconciles the Downes construction manager fee on the project. $33,447.13 CREDIT. p. 2
  4. Discussion and possible action on findings from commission testing done by CMTA, held November 2-5. p. 1
  5. Discussion and possible action on a stairwell nosing proposal from M. Frank Higgins. p. 1
  6. Discussion and possible action on scope of work done by Facilities, including glycol costs after Cooling Tower repairs and other remaining items. p. 1
  7. Update on the completed Cooling Tower modifications. p. 1
  8. Progress reports from Friar Architect, Colliers Project Leaders, and Downes Construction, plus school administration feedback. p. 1
  9. Approval of the minutes of the previous meeting, held October 5, 2026. p. 1
Words on this agenda, explained
Change order
A written change to the construction contract that adds or removes work and changes the price.
PCO
Potential change order: a proposed change to the construction contract that the board still has to approve.
Lump sum
One fixed total price for a job, not a price based on hours or units used.
Not-to-exceed amount
The most that can be paid for the work; the final cost should be at or below this number.
Commissioning
Testing that building systems, such as heating and cooling, work as they were designed to.
Glycol
A liquid added to cooling systems to keep the water from freezing.