Building Renovation Committee
Wed Nov 18 · 4 days ago
Building Renovation Committee Meeting
This agenda in plain words
Leer en españolThis is a regular monthly meeting of the Building Renovation Committee in the Town of Canton, Massachusetts, on Wednesday, November 18, 2026, at 7:00 PM. Most of the agenda is a status report on town and school building projects, with updates on each one. The main items are the Galvin Middle School project, the Library roof and interior work, and the Senior Center and Fire Department boiler projects.
- Status report on the Galvin Middle School building project. It covers the design contract, a change to grades 5-8, an 800-seat auditorium, and a construction contractor recommendation. The school building committee voted $241,764,835 for the project. $241,764,835. Touches: Galvin Middle School; families and students in the school district; Town of Canton taxpayers. p. 1
- Status report on the Library roof project. It covers the stone cornice repair, the Town Maintenance Dept taking over the HVAC work, and the project schedule. $4,280,000. Touches: Canton Public Library; library users. p. 2
- Status report on the Library interior renovation. It covers the low bid from Seaver Construction Co., the decision to leave out a new BMS system, and the construction start. $4,868,245. Touches: Canton Public Library; library users. p. 2
- Status report on the Senior Center HVAC replacement. It covers grant money, the new roof equipment problem, and the expected finish date. $401,320. Touches: Senior Center users, including Meals on Wheels. p. 2
- Status report on the Fire Stations boiler replacement. It covers engineering work and a request for $49,019 in cash capital for FY2027. $350,000. Touches: Fire Department. p. 3
- Status report on the Paul Revere Pavilion project. It covers a hired firm, drainage test pits, and a pending Conservation Commission permit. $200,000. Touches: Paul Revere Pavilion; Paul Revere Historical Trust (PRHT). p. 3
- Status report on the Fire Dept Study. Four bids were received, and the firm TGAS was selected. $96,000. Touches: Fire Department. p. 3
- Status report on the DPW Garage Roof project. The specifications are being written to go out to bid. $197,800. Touches: Department of Public Works (DPW). p. 3
- Review of the budget report on all project balances. The committee will recommend which balances on finished projects should go back to Free Cash at the next Annual Town Meeting. p. 3
Words on this agenda, explained
- ATM
- Annual Town Meeting, the yearly vote in which the town approves money for projects.
- OPM
- Owner's Project Manager, a firm hired to manage a building project for the town.
- BMS
- Building Management System, the computer system that controls a building's heating, cooling and other equipment.
- HVAC
- Heating, ventilation and air conditioning.
- Free Cash
- Money left over from past budgets that the town can use again.
Written by AI from the agenda, Nov 14. Each point links to its page: read it there before you rely on it. Nothing here says how the board will vote.
Agenda items (5)
- …y also voted for options # 9E, New vertical construction with an estimated cost of $223,000,000. The Subcommittee voted to recommend that the General Contractor be awarded to Consigli Construction. The School Building Committee voted $241,764,835 to be submitted to MSBA for the cost ofnew GMS School. Special Town Meeting is 11/18 and override vote is scheduled for 12/10/24 Project is on schedule. Town Meeting voted $241,764,835 Total. 218,350 Sq Ft building with Possible 72/73,000,000 reimbursement from the State ofMA. Work is progressing on schedule School building Committee, a subcommittee o… p. 1
- …timate is $4,106,919. Town Meeting voted $3,931,210 additional revenue for the project. The BRC selected Anser as our OPM and hired them at $169,065. Bids were received on 12/21 Greenwood Industries was the low bid at $3,043,000. RTU have arrived. Stone Cornices expected for next week Construction progressing on schedule. Two RFP’s are being worked on for the Interior ofthe Library and for the Library Park phase 1 at the front ofthe Library. Still working on completing Heating and cooling and Coordinating with the controls BRC voted 8-0-0 to exclude any upgrades on the heat side ofthis HVAC sy… p. 2
- …,868,245 BRC voted 8-0-0 to exclude a new BMS system into this project. Projected cost is $599,153. PM&C cost estimate of 12/15/25 is $4,435,506. Low Bid was Seaver Construction Co at $2,743,984 Under the estimate by $447,110 Reviewing 90% plans. CPL Pre-bid walkthrough was completed today 4/15/2026. • Filed Sub-Bid Due: Wednesday April 22 @ 2:00 PM, General Bid Due: Friday May 1 @ 1:00 PM. Construction will begin in Early July All subcontractors are under contract. All demo is complete, structural steel is in place awaiting ATS testing results and fireproofing this week. Temporary walls in lo… p. 2
- d. Senior Center HVAC Replacement ATM 25 Article 13 Motion 15 $401,320 Update: An Eversource Energy Efficiency incentive has been awarded toward the Control portion ofthis project on 6/30/2025 in the amount of $685. to be utilized by 1/30/2026. A Green Communities Grant was awarded for the Project on 8/12/2025. This grant included $186,599. For the VRF heat pump system. Also granted was $63,401. for the building management system (BMS) tie in to the VRF system. Total incentives awarded for this project $250,685. Vision Energy Systems is progressing on this project. This project is exempt for M… p. 2
- …ee ifthe current oil-fired boiler can be replaced at this price. Additional Capital in the amount of $203,981 (transfer upon completion of Sr. Center HVAC project from $250,000 grant award, and Cash Capital in the amount of $49,019 has been requested for FY2027. Fire Dept Boiler Replacement: ATM 26 Article 15 Motion 2 $49,019 ($201,981 from Senior center ATM 25 Article 13 Motion 15 + 100,000 ATM 25 Article 13 Motion 16 Total Cost $350,000 Working on Engineering Specifications. Eversource consulting on Service sizing and output Update Ongoing p. 3