Township of South Orange Village, NJ · pop. 18K
Wed15Jul7:00 PM
Transportation and Pedestrian Safety Committee
Wed Jul 15, 7:00 PM · 4 months ago
Agendasouthorangetwpnj.api.civicclerk.com
Minutesnot posted yet
Meeting page ↗southorangetwpnj.portal.civicclerk.comAgenda items (26)
- A.Councilwoman Summer Jones, Co-Chair Councilmember Olivia Lewis-Chang, Co-Chair Councilmember Bill Haskins, Co-Chair Julie Doran, Village Administrator Peter Travers, Deputy Administrator David Battaglia, Village Engineer Chief Dolinac, SOPD Sgt. Albino, Traffic Bureau Sgt. Lonero, SOPD Community Relations Joycelyn E. White, Recording Secretary p. 1
- A.April 15, 2026
- A.Special TAPS Safe Streets 4 All Meeting – Date TBA
- B.Bike Network Plan
- i.Survey Closed
- ii.Next Step:
- iii.Projected Completion: 12/31/2026 p. 1
- C.51-53 SOA - Demo & Sidewalk Restoration – w/o 7/13
- i.Greenway: Admin to consider micro-mobility device regulations/sharing the paths with pedestrians. p. 1
- D.Open Projects & Resident Inquiries Status Report — Attached p. 1
- A.Active Projects – See Open Projects List
- B.Upcoming Village Projects p. 1
- i.Greenway Phase 2 – Field construction slated to begin in August
- ii.Church & W. 3 rd will continue as planned/approved and funded. Project underway
- iii.3 rd & Ridgewood Signalization – Design pending
- iv.MCCPC Roads Repaving – On hold pending NJAW lead lines work. Anticipate August field work.
- v.MCCPC Roads Restriping – Field construction is expected to begin in September.
- vi.Grove Park Rehabilitation – Field construction slated to begin in 07/20/2026
- C.County 11 Intersections project
- i.Projected completion date: Requested project update p. 2
- ii.Dedicated Pedestrian Interval at Ridgewood & SOA — Confirmed p. 2
- iii.Other intersections to be observed and recommendations made post-project completion p. 2
- A.• 2026 Traffic Studies • Grant Applications • 2025 Crash Report Status • Other
- A.The Chair opens the meeting for public comments. p. 2
- A.October 15, 2026; 7pm p. 2
- A.Report a Concern - https://main.govpilot.com/web/public/a6d46fe8-29f_SO-Connect-southorangevillage?uid=6977&ust=NJ&pu=1&id=0#D&reserved=0 Roads Projects - https://www.southorange.org/654/South-Orange-Village---Roads-Repaving Traffic Studies - https://www.southorange.org/986/Traffic-Studies