Agendabarringtonboro.comMinutesbarringtonboro.comAgendaAugust 2026 Engineer ReportMeeting page ↗barringtonboro.com
1 item on this agenda matches the land-use topicsData centers & plants (1)
Agenda items (7)Show only the 1 matching
- …for Recreational Opportunity for Individuals with Disabilities FY 2027 Grant • Resolution for Planning Board – Review and Recommendation to Prohibit Data Centers and permitting additional Cannabis Classes in M-2 zone. • Resolution for Planning Board – Preliminary Investigation of M-2 Manufacturing District for determination as redevelopment or in need of rehabilitation • Refund Duplicate Wedding Ceremony Fee • Authorizing Contract with PSE&G for Energy Saver Program – Program to replace Roof Top A/C Unit where the Borough is responsible for 54.59% of the project. • Authorize Sale of Fire Depa… p. 2
- …the “Improvements to Devon Road from Hutchinson Avenue (C.R.665) to Tavistock Boulevard.” At the Council Meeting of May 12, 2026, the Governing Body awarded a contract to Asphalt Paving Systems, Inc. of Hammonton, New Jersey in the amount of $342,800.00. The contractor completed the Full Depth Reclamation (F.D.R.), topsoiling, concrete improvements and asphalt base course. We are currently processing Voucher No. 1 and Change Order No. 1 for review and consideration by the Governing Body at the Council Meeting of August 11, 2026. p. 2
- …orough received an allotment of $268,146.00 for the “Improvements to Austin Avenue – Phase 4, from Fourth Avenue to Fifth Avenue”. The Governing Body awarded a contract to DiMeglio Construction Company, Inc., of Atco, New Jersey in the amount of $353,860.50 at the Council Meeting of October 14, 2025. The contractor has removed the trees and completed the replacement of approximately 120 linear feet of sanitary sewer main. New Jersey American Water has replaced a section of water main. On July 20, 2026, the contractor commenced with concrete improvements. We are currently processing Voucher No.… p. 3
- 5. OAK AVENUE STORM SEWER PIPE LINING – PHASE 1 (KEI #11-489BR0624): The Governing Body awarded a contract to Think Pavers Hardscaping, LLC of Mount Royal, New Jersey in the amount of $103,427.50 (Base Bid Only). p. 4
- 6. IMPROVEMENTS TO SECOND AVENUE, FROM TRENTON AVENUE TO ERIE AVENUE AND BELL AVENUE, FROM WHITE HORSE PIKE TO BAPTISTE AVENUE (KEI #11-486BR0324): The Governing Body awarded a contract to Landberg Construction, LLC of Dorothy, New Jersey in the total combined amount of $392,746.68 ($345,118.33 for Base Bid ‘A’ and $47,628.35 for Base Bid ‘B’). The contractor has completed the project with the exception of any punch list items requiring rework and/or correction. p. 5
- 7. MUNICIPAL BUILDING PARKING LOT IMPROVEMENTS (KEI #11-497BR0825): At the Council Meeting of September 9, 2025, the Governing Body awarded a contract to Landberg Construction, LLC of Dorothy, New Jersey in the total combined amount of $312,741.57 ($186,974.43 for the Base Bid and $125,767.14 for Alternate No. 1). The project will be constructed in phases, so that the Municipal Building operations will not be effected. On July 22, 2026, the contractor commenced with the parking lot paving improvements. The contractor has completed the project with the exception of lawn restoration, line stripi… p. 5
- …erintendent of Public Works Mr. Robert Harris, Construction Department Manager Ms. Eileen E. Holcombe, Executive Secretary Ms. Kate Bowen, Barrington Ambulance Captain Projects/11/Reports/2026/August p. 7