- a.Minutes from Caucus and County Council September 14, 2026. - N/A
- a.Proclamation recognizing the Week of October 18–24 as National Friends of Libraries Week. p. 1
- b.Proclamation recognizing Kraig Gordon. p. 1
- a.Public Comment
- Community Services Committee p. 1
- Natural Resources Committee p. 1
- Finance, Administration, and Economic Development Committee p. 1
- Public Facilities Committee p. 1
- a.Items Originating from the Public Facilities and Safety Committee p. 2
- 1.Approval of task order to Collins Engineers, Inc for the design of improvements and expansion of the Eddings Point Boat Landing ($233,912.80) (Pending A&H Tax awards on 9/14/26) - The Edding's Point Boat Landing was identified in the Beaufort County Public Boat Landing Facilities Study as a high-priority for future expansion. It is one of the busier boat landings in the County and lacks adequate parking and amenities. The project was selected for FY 2026 ATAX funding. Collins Engineers, Inc was one of three consultants selected in the competitively bid RFQ # 040726 On-Call Marine and Coastal Engineering Services p. 2
- 2.Approval of a change order to MAJ Enterprises, Inc. for the Shell Point Traffic Calming Project ($53,592.09) - On February 18, 2026 Beaufort County published an Invitation for Bid (IFB) # 032326 Shell Point Traffic Calming requesting competitive bids for materials and installation of traffic calming measures in the Shell Point neighborhood. Due to a resident complaint, one of the speed humps was moved to be further from their driveway. Also, a catch basin was discovered at Broad River Drive and Shell Point Road that required a traffic rated solid lid for the raised intersection. Additionally, construction quantities were substantially higher than estimated for the Asphalt Surface Course. Due to these factors, the costs have exceeded the contract amount. p. 2
- 3.Recommendation to Award a contract to Apac Atlantic, Inc for the Sunset Blvd / Miller Drive roadway resurfacing and traffic calming project ($739,873.48) - This project is part of the 2018 Sales Tax Program and is governed by an encroachment permit between SCDOT and Beaufort County. Project includes resurfacing of 0.35 miles of Sunset Boulevard (S-186) & Miller Drive West (S-187) Project. (Sunset blvd from Sea Island Parkway to intersection of Miller Drive West and Miller Drive West from Sunset Boulevard to Sam’s Point Road). Traffic calming installation within the project roadways is also included within the scope of work. p. 2
- 4.Approval of a Task Order to HDR Engineering, Inc for the Preliminary Engineering for Alterations to the Chowan Creek Bridge Approaches ($212,630) - The Chowan Creek bridge has been noted as a choke point along US 21 on St. Helena Island in emergency situations. The bridge was also identified in the Beaufort County Roadway Vulnerability Study completed in 2025. The project has been included in the 2026 Transportation Sales Tax referendum. This task order will enable the County to begin preliminary engineering and design for alterations to provide congestion relief during emergency situations. The concept will be to restipe the bridge to allow for a center median and widen the approaches on both sides for the additional lane width requirements. HDR Engineers, Inc was one of ten consultants selected in the competitively bid RFQ # 032626 On-Call Transportation Roadway Design. p. 2
- 5.Omnia contract award for St. Helena Island Library LED retrofit ($200,000). - The interior lighting system at St. Helena Library is very complex and in need of repair; the parts are obsolete and no longer available. Completing an LED lighting retrofit is the only solution available to restore the interior lighting to working condition. Two local and one national vendors declined to provide a proposal due to the complexity of the project. We were able to secure one proposal with Graybar through an Omnia based contract. p. 2
- 6.Recommendation for approval of a change order with Kimley Horn for a Phase 2 Environmental Site Assessment (ESA) on the Ladys Island Drive Turn Lane at Ribaut Road Project ($42,350) - The task order with Kimley Horn for design services of a right turn lane on Ladys Island Drive to Ribaut Road requires right of way from the adjacent property where a gas station was previously operated. The Phase 1 Environmental Site Assessment found that contamination is likely, which requires a Phase 2 ESA to determine the extent of the contamination and potential mitigation. p. 2
- a.2026/43: An ordinance to amend Ordinance 2026/29 to authorize the transfer of funds. The vote at the Finance, Administration, and Economic Development Committee on August 17, 2026 - 9:0 The vote at First Reading on September 14, 2026 - 9:1 The vote at Second Reading and Public Hearing September 28, 2026 - 6:4 - Language authorizing the transfer of funds was removed from the FY27 Budget Ordinance. This means that no movement of funds between departments or within the CIP funds can occur without Council approval. There are currently several CIP projects that are on hold until additional funding can be approved. There are many projects that are complete with project savings available to provide funding for these projects. Staff have provided three options that would restore authority to approve budget transfers for the County Administrator or CFO. The approval of one of these options would … p. 2
- b.…process, totaling $7,247,672.28. The details of the transfers are as follows: (1) $3,475,000 from the Stormwater Utility Enterprise Fund for the Stormwater Utility operational budget; and (2) $1,916,589.12 from A-Tax to fund 2 carryover Purchase Orders that were planned in the prior fiscal year but not adequately budgeted in FY2027($642,489.12), support for the Waterfront Park project ($1,000,000), and 15% of A-Tax for to support affordable housing ($274,100) (3) $1,000,000 from H-Tax to support the Waterfront Park project (4) $539,900 from Parks & Rec Impact Fees to fund a carryover Purchase Orders that was planned in the prior fiscal year but not adequately budgeted in FY2027 (5) $62,914.06 in Airport Funds to fund a carryover Purchase Orders that was planned in the prior fiscal year but not adequately budgeted in FY2027 and (6) $253,269.10 from the General Fund fund balance for the p. 2
- c.2026/45: An Ordinance Authorizing the County Administrator to Execute the Necessary Documents and Provide Funding for the Purchase of Real Property Identified as TMS Nos. R200-010-000-0340-0000, R200-010-000-021G-0000, and R200-010-000-0446-0000 from Brickyard Commons, LLC for the Royal Pines Stormwater Project in the amount of $3,475,000. The vote at the Finance, Administration, and Economic Development Committee meeting on August 17, 2026 - 9:0 The vote at First Reading on September 14, 2026 - 10:0 The vote at Second Reading and Public Hearing on September 28, 2026 - 10:0 - Beaufort County has identified the southern Royal Pines area as an area of known drainage concern, and the area was evaluated as part of the Northern Lady's Island Drainage Study completed in May 2024. Last fall, a developer, Brickyard Commons, LLC, approached the County with an unsolicited public-private… p. 2
- d.2026/46: An Ordinance Authorizing the County Administrator or negotiating authority in accordance with Resolutions 2019/44 and 2021/20 to execute any and all necessary documents for the acceptance of Right of Way and/or Temporary Construction Easement properties as shown on EXHIBIT A Pages 1-4 associated with the Sidewalks and Multi-use Pathways – Safe Routes to Schools and EXHIBIT A Pages 5-8 associated with the Lady’s Island Corridor Traffic Improvements. The vote at the Public Facilities Committee Meeting on August 17, 2026 - 9:0 The vote at First Reading on September 14, 2026 - 10:0 The vote at Second Reading and Public Hearing on September 28, 2026 - 10:0 - Per Resolution 2019/44 for the 2018 One Percent (1%) Transportation Sales and Use Tax which states “County Council authorizes the acquisition of all rights-of-way needed by way of negotiations by agents or administrators of… p. 2
- a.2026/47: An Ordinance authorizing the County Administrator to execute an Electric Line Easement with Dominion Energy on the property known as Pocotaligo Preserve (TMS R710 012 000 0001 0000 and R710 012 000 0072 0000). The vote at Natural Resources Committee on September 8, 2026 - 7:0 The vote at First Reading on September 28, 2026 - 10:0 - Beaufort County owns in fee-simple the property known as Pocotaligo Preserve located at 30 Cotton Hall Road in Yemassee, SC. Dominion Energy owns an overhead electric line that runs through various open fields on the property, which is negatively impacted by County-initiated land management activities. Due to the length of time the original easement agreement was executed by prior property owners, and the desire by both the County and Dominion to relocate the electric line to a more suitable location along the property access road, the execution of a … p. 3
- b.2026/48: An Ordinance amending the Beaufort County Code of Ordinances, Chapter74 - Building and Building Regulations, Section 74-64, Adoption of Building Codes (Amends Code of Ordinances to adopt the 2024 State Mandated Code Editions). The vote at Natural Resources Committee on September 8, 2026 - 7:0 The vote at First Reading on September 28, 2026 - 10:0 - On August 26, 2025, the South Carolina Building Codes Council (the "Council") adopted the latest editions of the mandatory code and appendices with modifications, as referenced in S.C. Code Ann. §6-9-50 (1976, as amended), to be enforced by all municipalities and counties in South Carolina. The Council established the implementation date for local jurisdictions as January 1, 2027. Local adoption of the latest state mandated code editions is required by state law. p. 3
- a.2026/49: An Ordinance authorizing the private road acceptance of Bellinger Bluff Road and Bellinger Neck Road into the County Road Inventory. The vote at Public Facilities Committee on September 21, 2026 - Failed 3:7 - Bellinger Bluff Road and Bellinger Neck Road are unpaved private roads and have a combined estimated length of approximately 0.35 miles. The Engineering Department estimates that paving costs could be $1,328,950.81. This is based on the County's most recent dirt road paving cost averages and an additional 3% inflation applied over 10 years. The Public Works Department has determined the estimated roadside cleaning costs for the roads can cost up to $20,000. The abutting property owners have petitioned the County to bring the private roads of Bellinger Bluff Road and Bellinger Neck Road into the County’s Road inventory. p. 3
- b.2026/50: An Ordinance to amend Beaufort County's Budget Ordinance for Fiscal Year 2027 (Ordinance No. 2026/29) to amend Section III, County Operations Revenues, and Section IV, County Operations Appropriations to appropriate Fund Balance for Beaufort County Regions Tournament Complex. The vote at Finance, Administration, and Economic Development Committee on September 21, 2026 - Failed 5:5 - Beaufort County has identified an unappropriated fund balance of $9,788,000 in Local Accommodation Tax (Fund 2001) and an unappropriated fund balance of $8,842,000 in Local Hospitality Tax (Fund 2002). The County has indicated an interest in developing a Regional Tournament Complex and hereby appropriates $15,000,000 of fund balance ($7,500,000 from Local Accommodation Tax) and ($7,500,000 from Local Hospitality Tax) to develop and construct a Regional Tournament Complex. p. 3