- a.2018 Sales Tax Quarterly Update (For Information Only) - In 2018, the citizens of Beaufort County voted to impose a 4 year, $120M referendum for transportation projects. The projects are as follows: US 278 Corridor Traffic Improvements, Lady’s Island Corridor Traffic Improvements, Sidewalks and Multi-Use Pathways
- b.Due diligence regarding the Lobeco Library in coordination with the School District. - At the Finance, Administration, and Economic Development Committee Meeting on August 17, 2026, the committee directed the County Administrator and staff to conduct due diligence regarding the Lobeco Library in coordination with the School District. p. 1
- c.Approval of task order to Collins Engineers, Inc for the design of improvements and expansion of the Eddings Point Boat Landing ($233,912.80) (Pending A&H Tax awards on 9/14/26) - The Edding's Point Boat Landing was identified in the Beaufort County Public Boat Landing Facilities Study as a high-priority for future expansion. It is one of the busier boat landings in the County and lacks adequate parking and amenities. The project was selected for FY 2026 ATAX funding. Collins Engineers, Inc was one of three consultants selected in the competitively bid RFQ # 040726 On-Call Marine and Coastal Engineering Services p. 1
- d.Approval of a change order to MAJ Enterprises, Inc. for the Shell Point Traffic Calming Project ($53,592.09) - On February 18, 2026 Beaufort County published an Invitation for Bid (IFB) # 032326 Shell Point Traffic Calming requesting competitive bids for materials and installation of traffic calming measures in the Shell Point neighborhood. Due to a resident complaint, one of the speed humps was moved to be further from their driveway. Also, a catch basin was discovered at Broad River Drive and Shell Point Road that required a traffic rated solid lid for the raised intersection. Additionally, construction quantities were substantially higher than estimated for the Asphalt Surface Course. Due to these factors, the costs have exceeded the contract amount. p. 1
- e.Recommendation to Award a contract to Apac Atlantic, Inc for the Sunset Blvd / Miller Drive roadway resurfacing and traffic calming project ($739,873.48) - This project is part of the 2018 Sales Tax Program and is governed by an encroachment permit between SCDOT and Beaufort County. Project includes resurfacing of 0.35 miles of Sunset Boulevard (S-186) & Miller Drive West (S-187) Project. (Sunset blvd from Sea Island Parkway to intersection of Miller Drive West and Miller Drive West from Sunset Boulevard to Sam’s Point Road). Traffic calming installation within the project roadways is also included within the scope of work. p. 2
- f.Approval of a Task Order to HDR Engineering, Inc for the Preliminary Engineering for Alterations to the Chowan Creek Bridge Approaches ($212,630) - The Chowan Creek bridge has been noted as a choke point along US 21 on St. Helena Island in emergency situations. The bridge was also identified in the Beaufort County Roadway Vulnerability Study completed in 2025. The project has been included in the 2026 Transportation Sales Tax referendum. This task order will enable the County to begin preliminary engineering and design for alterations to provide congestion relief during emergency situations. The concept will be to restipe the bridge to allow for a center median and widen the approaches on both sides for the additional lane width requirements. HDR Engineers, Inc was one of ten consultants selected in the competitively bid RFQ # 032626 On-Call Transportation Roadway Design. p. 2
- g.Omnia contract award for St. Helena Island Library LED retrofit ($200,000). - The interior lighting system at St. Helena Library is very complex and in need of repair; the parts are obsolete and no longer available. Completing an LED lighting retrofit is the only solution available to restore the interior lighting to working condition. Two local and one national vendors declined to provide a proposal due to the complexity of the project. We were able to secure one proposal with Graybar through an Omnia based contract. p. 2
- h.Recommendation for approval of a change order with Kimley Horn for a Phase 2 Environmental Site Assessment (ESA) on the Ladys Island Drive Turn Lane at Ribaut Road Project ($42,350) - The task order with Kimley Horn for design services of a right turn lane on Ladys Island Drive to Ribaut Road requires right of way from the adjacent property where a gas station was previously operated. The Phase 1 Environmental Site Assessment found that contamination is likely, which requires a Phase 2 ESA to determine the extent of the contamination and potential mitigation. p. 2
- i.An Ordinance authorizing the private road acceptance of Bellinger Bluff Road and Bellinger Neck Road into the County Road Inventory - Bellinger Bluff Road and Bellinger Neck Road are unpaved private roads and have a combined estimated length of approximately 0.35 miles. The Engineering Department estimates that paving costs could be $1,328,950.81. This is based on the County's most recent dirt road paving cost averages and an additional 3% inflation applied over 10 years. The Public Works Department has determined the estimated roadside cleaning costs for the roads can cost up to $20,000. The abutting property owners have petitioned the County to bring the private roads of Bellinger Bluff Road and Bellinger Neck Road into the County’s Road inventory. p. 2