Agenda items (38)Show only the 4 matching
- 1)Prayer
- 2)Pledge
- 3)Agenda Approval
- 1)UPCOMING on August 13: Center for Independent Living p. 1
- 2)UPCOMING on August 13: Recognizing the 100th birthday of Vincent Therrien p. 1
- 1)Congressman Jimmy Patronis p. 1
- 1)Public Input - Online Form
- 1)Check Register - Approval of the check register from July 12, 2026 through August 2, 2026.
- 2)Minutes - Approval of the minutes from the June 22, 2026 BOCC Regular Meeting, June 22, 2026 BOCC Special Meeting, July 9, 2026 BOCC Budget Workshop, and the July 23, 2026 BOCC Special Meeting.
- 1)Administration - CareerSource Escarosa Board Membership Request - Approval or denial to appoint Jennifer Hines to the CareerSource EscaRosa Board of Directors. p. 1
- 2)Administration - Navarre Beach Fire Rescue District Request Loan from BOCC - Approval or denial of the Navarre Beach Fire Rescue District's request for a loan of $300,000 from Santa Rosa County. p. 2
- 3)Administration - PPBEP Letter of Support for NEP Nomination - Approval or denial of a Letter of Support to U.S. Environmental Protection Agency Administrator Lee Zeldin for the Pensacola and Perdido Bays Estuary Program's (PPBEP) National Estuary Program Nomination and Enrollment. p. 2
- 1)No items.
- 1)Administration - 2026 FDEP Resilient Florida Grant on Behalf of East Milton Water System - Approval or denial to submit a 2026 Florida Department of Environmental Protection (FDEP) Resilient Florida Grant application on behalf of the East Milton Water System (EMWS), and authorization for the chairman to sign all related documents. p. 2
- 2)Environmental - Annual Detailed Work Plan Budget for Mosquito Control - Approval or denial to submit the annual mosquito control detailed work plan budget to FDACS for FY 2026 - 2027 and authorize the chairman to sign all related documents. p. 2
- 3)Environmental - Central Landfill Pre-Development Engineering Services Task Order - Approval or denial of Task Order # GEO26-01 for 20-038 to Geosyntec Consultants, Inc in the amount of $149,000 for Central Landfill pre-development engineering services and authorization for the chairman to sign all related documents. p. 2
- 4)Environmental - Eglin Regional Reuse (RIBs) Project Contract Award - Approval or denial to contract with Gulf Coast Utility Contractors in the amount of $15,975,250 as the apparent low bidder for ITB 26-039 Regional Reuse System Phase 2, and authorization for the chairman to sign all related documents. p. 2
- 5)Environmental - FPL Easement & Utility Infrastructure for the Milton Interchange Park WWTP - Approval or denial of a utility infrastructure easement, along with authorization of payment to FPL in the amount of $54,189.73 for underground electrical utility work associated with the Milton Interchange Park Wastewater Treatment Plant, and authorization for the chairman to sign all related documents. p. 2
- 6)Environmental - Navarre Beach Dune Restoration - FDEP FY 2027/2028 Local Government Funding Resolution - Approval or denial of a resolution affirming that Santa Rosa County will serve as the local sponsor for the required construction and monitoring of the Navarre Beach Dune Restoration Project and authorizing the chairman to sign all related documents. p. 2
- 7)Environmental - RT038 FDEP Red Tide or Other Nuisance Marine Algae Grant - Approval or denial to execute a grant agreement with FDEP to receive up to $100,000 of reimbursement for FDEP-approved expenses as a result of biological debris removal associated with red tide or other nuisance marine algae, and authorization for the chairman to sign all related documents. p. 2
- 8)Engineering – Ashley Plantation Drainage Improvements Time Only Change Order 5 - Approval or denial of Change Order #5 for 24-024 with Chavers Construction to add 23 days to the contract for Ashley Plantation Drainage Improvements to incorporate weather and utility days, and authorization for the chairman to sign all related documents. p. 3
- 9)Engineering - Pine Blossom Drainage Construction Change Order 4 - Approval or denial of Change Order #4 for 25-012 with Bear General Contractors to add 36 days to the contract for the Pine Blossom Road Drainage Improvements for observed holidays and weather delays and authorization for the chairman to sign all related documents. p. 3
- 10)Engineering –Pine Blossom Construction Administration Change Order 1 - Approval or denial of Change Order No.1 to Volkert for the reallocation of funds from Task Order #21-006-VOL-001A to Task Order 24-014-VOL-8 in the amount of $50,148, and authorize the chair to sign all related documents. p. 3
- 11)Engineering - Oriole Beach Elementary Drainage Construction Change Order 1 - Approval or denial of Change Order #1 to Roads Inc. for additional work to address three outfalls at the retention pond to prevent continued erosion and stabilize slopes at a cost of $15,590.40, and authorization for the chairman to sign all related documents. p. 3
- 12)Engineering - Archie Glover Channel Maintenance Change Order 1 - Approval or denial of change order #1 to Complete Site Source LLC for additional work outside of original bid scope to remove 200 linear feet of submerged 8” dredging pipe and submerged, broken channel marker poles at a cost of $10,000.00, and authorization for the chairman to sign all related documents. p. 3
- 13)Engineering - Molino Bridge Supplemental Design Task Order - Approve or denial of supplemental task order #2 to Southern Site & Utility Design (SSUD) in the amount of $135,000 and authorize the chair to sign all related documents.
- 14)Engineering - Construction Contract for CR 182 Widening & Resurfacing (LAP) - Approval or denial of the contract award (ITB 26-021) to Panhandle Grading and Paving for CR 182 Widening & Resurfacing (LAP) in the amount of $3,434,569.97 as the apparent low bidder and authorize the Chair to sign all related documents. p. 3
- 15)Housing - Manufactured Housing Strategy Addition to the Local Housing Assistance Plan - Approval or denial of the Manufactured Housing Strategy as required by Senate Bill 594 and pre-approved by the Florida Housing Finance Corporation (FHFC), and authorization for the chairman to execute all required documentation necessary for submission of the amended LHAP to FHFC. p. 3
- 16)Public Safety - FDOT Disaster Response Staging - Approval or denial of a License Agreement with Florida Department of Transportation for disaster response staging within a portion of East Milton Park, and authorization for the chairman to sign all related documents.
- 17)Public Works - Vehicle Transfers to Enterprise Fleet Services - Approval or denial to declare the listed vehicles as surplus property and authorize the transfer of these assets to Enterprise Fleet Management for sale, and authorization for the chairman to sign all related documents. p. 3
- 18)Public Works - Installation of Fencing in County-Owned ROW (Woodlawn Heights HOA) - Approval or denial for the Woodlawn Heights Homeowners Association to construct and maintain a privacy fence on county-owned right-of-way, and authorization for the chairman to sign all related documents. p. 3
- 19)Public Works - Open Cut (Pennsylvania Ave.) - Approval or denial to allow Utility Service Co., Inc. to perform an open cut for City of Gulf Breeze’s Tiger Point Ceylon lift station project, and authorization for the chairman to sign all related documents.
- 20)Public Works - Open Cuts - North Avalon Beach - Approval or denial to allow Pace Water System to perform open cuts for a low-pressure sewer installation in the area of north Avalon Beach, and authorization for the chairman to sign all related documents. A full list of associated roads is provided in the item backup.
- 1)OMB - Budget Amendment 2026-054 NWFWMD Grant Award - Approval or denial of Budget Amendment 2026-054 for the NWFWMD Grant Award recognizing the grant award in the amount of $1,000,000 towards residential conversions from septic to Distributed Wastewater Treatment Units within the Blackwater River Basin, and authorization for the chairman to sign all related documents.
- 2)OMB - City of Gulf Breeze Subrecipient Agreement for NRDA DWH FDEP Grant Award DH022 - Approval or denial of a sub-recipient agreement with the City of Gulf Breeze in the amount of $6,002,948 to carry-out septic to sewer conversions as defined in the NRDA Deepwater Horizon FDEP grant award DH022 work plan, and authorization for the Chair to sign all related documents. p. 4
- 3)OMB - Local RESTORE Council Appointment and Term Renewal - Approval or denial to renew the terms (2 years) of the following LRC members: Jeremy Tompkins (D1), Time Wheat (D3), Dave Robau (D5), and Samantha Abell (City of Gulf Breeze).
- 4)OMB - Metron Estates Change Order #2 - Approval or denial of Change Order #2 for 23-013 with Pegasus Engineering to add $14,970 to the contract for the FEMA Metron Estates Phase 2 Grant Management Services for the final deliverables and closeout using final SRMC funding allotment and authorization for the chairman to sign all related documents.
- 1)Upcoming Meetings - August 13 @ 8:30 AM Commission Regular Meeting August 13 @ 5:00 PM Zoning Board Meeting August 19 @ 5:00 PM Aviation Advisory Committee August 25 @ 8:30 AM Commission Committee Meeting Tiger Point Community Center, 1370 Tiger Park Ln, Gulf Breeze, FL 32563 August 27 @ 8:30 AM Commission Regular Meeting August 27 @ 5:00 PM Commission Special Rezoning Board Meeting