Board of Public Works Meeting
Agendafortwaynein.api.civicclerk.comMinutesfortwaynein.api.civicclerk.comRecording ▸fortwaynein.portal.civicclerk.comAttachment67086 - Anthony Lake to Vance 24 Inch Water MainMeeting page ↗fortwaynein.portal.civicclerk.com
1 item on this agenda matches the land-use topicsWater & sewer (1)
Agenda items (49)Show all 49
- 17.Approval of Change Order #1 & Final between the City of Fort Wayne and S&S Directional Boring for Contract #67086, Anthony - Lake to Vance 24" Water Main Extension. This change order increases the original contract price by $322,266.28 to a final contract price of $2,818,316.28 and extends the completion date by187 days. p. 1