- E. NEW BUSINESS E.1 Interim Urgency Ordinance 2026-08 CM Temporary Moratorium for Data Centers Pursuant to Government Code 65858 Adopting an Interim Urgency Zoning Ordinance Establishing a Moratorium on the Acceptance, Processing, and Approval of Applications and Entitlements for Data Centers to Allow for the Evaluation of Potential New Land Use Regulations, and Impacts Related to Public Health and Utilities Funding Source: N/A Contact: David Gassaway, (707) 428-7400 Recommended Action: Consider Interim Urgency Ordinance 2026-08 and take action to implement or reject urgency ordinance; provide… p. 2
- …ne. Speakers are limited up to three minutes per item, as determined by the mayor. E. NEW BUSINESS E.1 Interim Urgency Ordinance 2026-08 CM Temporary Moratorium for Data Centers 1. Agenda Report CM Data Center.pdf 2. Proposed Urgency Ordinance 2026-08.pdf Pursuant to Government Code 65858 Adopting an Interim Urgency Zoning Ordinance Establishing a Moratorium on the Acceptance, Processing, and Approval of Applications and Entitlements for Data Centers to Allow for the Evaluation of Potential New Land Use Regulations, and Impacts Related to Public Health and Utilities Funding Source : N/A Contac… p. 1
- E. NEW BUSINESS E.1 Interim Urgency Ordinance 2026-08 CM Temporary Moratorium for Data Centers 3 Pursuant to Government Code 65858 Adopting an Interim Urgency Zoning Ordinance Establishing a Moratorium on the Acceptance, Processing, and Approval of Applications and Entitlements for Data Centers to Allow for the Evaluation of Potential New Land Use Regulations, and Impacts Related to Public Health and Utilities Funding Source: N/A Contact: David Gassaway, (707) 428-7400 Recommended Action: Consider Interim Urgency Ordinance 2026-08 and take action to implement or reject urgency ordinance; provi… p. 2
- …GENDA REPORT DATE: November 10, 2026 TO: Mayor and Council FROM: David Gassaway, City Manager SUBJECT: Interim Urgency Ordinance 2026-08 CM Temporary Moratorium for Data Centers Pursuant to Government Code 65858 Adopting an Interim Urgency Zoning Ordinance Establishing a Moratorium on the Acceptance, Processing, and Approval of Applications and Entitlements for Data Centers to Allow for the Evaluation of Potential New Land Use Regulations, and Impacts Related to Public Health and Utilities Funding Source: N/A Contact: David Gassaway, (707) 428-7400 RECOMMENDED ACTION Consider Interim Urgency O… p. 3
- A “data center” is a physical facility or building that houses computer systems, processors, servers, storage drives, and networking equipment used to store, process, and move digital information. Data centers typically use a large amount of energy to power their technology and require cooling systems such as air conditioning or water-based cooling systems to remove the heat generated by the technology. The proliferation of data centers as a land use is a relatively new phenomenon and is therefore not specifically included in the land use planning provisions of the last update to the Fairfield… p. 4
- …maps, general plan or zoning amendments, development agreement, grading permit, building permit, certificate of occupancy, or business license for a data center. The council would be required to pass any such urgency ordinance by a 4/5 vote (six of seven councilmembers). The council may extend the initial 45-day ordinance for up to 22 months upon a subsequent vote. Additionally, within 10 days of the expiration of the interim ordinance, City staff must submit a written report describing the measures taken to alleviate the conditions which led to the adoption of the interim ordinance. If the c… p. 5
- …Fairfield Ordinance No. 2026-08 Pursuant to the California Government Code Section 65858 Adopting an Interim Urgency Zoning Ordinance Establishing a Moratorium on the Acceptance, Processing, and Approval of Applications and Entitlements for Data Centers to Allow for the Evaluation of Potential New Land Use Regulations, and Impacts Related to Public Health and Utilities the City Council of the City of Fairfield Does Ordain as Follows: Section 1. This Ordinance Is Adopted Pursuant to Section 65858 of the Government Code of California and All Applicable Laws. Section 2. Findings. the City Counci… p. 7
- A. Data centers are facilities used to house computer systems, servers, data-storage equipment, telecommunications equipment, and related components. Demand for large-scale data centers has substantially increased due to the growth of cloud computing, digital commerce, artificial intelligence, and other data-intensive technologies. p. 7
- B. Large-scale data centers may require substantial quantities of electricity and water to operate and cool computing equipment; may impose significant demands on public utilities and infrastructure; and may raise land use compatibility concerns related to noise, air quality, and aesthetics. p. 7
- D. The Fairfield Municipal Code does not list, nor does it regulate data centers as a land use within the City. In evaluating existing Zoning Ordinance regulations, the City has determined that a data center may be interpreted as a “Wholesale, Storage, and Distribution. Heavy” use for which it is permitted by right in the IG (General Industrial) District and conditionally permitted in the IL (Limited Industrial) District. p. 7
- F. Data center development would create a current and immediate threat to the public health, safety, and welfare by causing significant impacts related to energy consumption, water, wastewater, land use, air emissions, noise, infrastructure demands, environmental quality, and community aesthetics. Approval of a data center project could materially reduce City services available to serve residents, businesses, and other existing and planned uses. p. 8
- G. The City is in the preliminary stages of studying data centers, their impact on City services and surrounding communities and what zoning regulations are warranted to address these impacts. The City intends to complete this study, and to determine whether additional regulations are warranted, within a reasonable amount of time. p. 8
- H. Without a temporary moratorium, the City may be required to approve a data center project before completing studies and adopting regulations necessary to evaluate and mitigate potentially significant impacts. This could adversely affect the City’s ability to provide essential public services. p. 8
- I. Adoption of this Interim Ordinance is necessary to protect the City and its residents, businesses, and visitors from the potential public health, safety, and welfare impacts associated with data center land uses. p. 8
- J. The moratorium will provide the City with sufficient time to study potential impacts of data centers and prepare comprehensive regulations governing the location, design, operation, water and energy use, infrastructure requirements, and other development standards applicable to data center uses. p. 8
- K. The City Council finds that there is a current and immediate threat to the public health, safety, and welfare of the City, and that the approval of entitlements and permits for data centers would result in that threat to the public health, safety, and welfare as detailed under Government Code Section 65858(c). SECTION 3. The following provisions are hereby adopted as interim zoning standards pertaining to the review or approval of any entitlements or the issuance of any permits pursuant to the Fairfield Municipal Code for a “Data Center” (as defined herein): p. 8
- A. Definitions. For the purposes of this Ordinance, “Data Center” shall mean a building or structure, or portion, or group thereof, designed or used primarily to house computer systems, servers, data storage, or network equipment, and associated electrical and cooling infrastructure, with 5,000 square feet or more of gross floor area devoted to that use or a designed electrical load of one (1) p. 8
- ORD. NO. 2026-08 Page 3 megawatt or more. Energy facilities to serve a data center, such as on-site battery storage or backup generation, would also be subject to the proposed moratorium. The term does not include server, computer, or telecommunications equipment that is accessory and incidental to a lawfully established principal use on the same parcel, or wireless telecommunications facilities whose primary purpose is transmitting signals rather than housing servers or data storage equipment. p. 9