Missoula County, MT · pop. 120K
Tue11Aug10:00 AM
BCC Admin Meetings
Tue Aug 11, 10:00 AM · 3 months ago
Commissioners' Administrative Meeting
Agendamissoulacomt.api.civicclerk.comMinutesmissoulacomt.api.civicclerk.comMeeting page ↗missoulacomt.portal.civicclerk.com
1 item on this agenda matches the land-use topicsSubdivisions (1)
Agenda items (8)Show only the 1 matching
- Hybrid meeting: You can attend in person in Conference Room 206 of the Missoula County Administration Building (199 W. Pine st) or virtually by using our Microsoft Teams link found here: http://missoula.co/bccpublicmeeting p. 1
- 1.Request board approve Phase III Construction Administration services for Lolo Street Bridge. - Request board approve Phase III Construction Administration services for Lolo Street Bridge. The FHWA executed the final grant amendment, and we can now move forward with bidding the project. The total amount of this agreement is $198,186 and covers construction administration and oversight for the bidding process. p. 1
- 2.Request board approve purchase of new 9-1-1 Center consoles from Watson Consoles in the amount of $203,971.50. - IN FY 26 the Board approved a budget enhancement to replace the 9-1-1 Center Consoles. Watson Consoles was selected due to existing console manufacturer as well has having NASPO pricing and State contracts in place. Due to several factors these consoles were not purchased in FY26 but final design and configuration are now complete and we anticipate installation occurring within the next several months if approved. p. 1
- 3.…Department dba Missoula Public Health for sanitation in subdivision reviews for divisions of land in Missoula County. Compensation is between $20,000 and $25,000 per year. - State law allows local health departments to contract with the Montana Department of Environmental Quality (DEQ) to review certain Sanitation in Subdivision applications. MPH has several DEQ-approved reviewers, who ensure that subdivision proposals meet the minimum criteria for water, wastewater, non-degradation standards, storm water and solid waste disposal. Reviewing them locally is preferred because the reviewers go out to each site, know more about groundwater, soils and other complicating site conditions, and understand how to apply local rules. The attached Contract is for review only. The final Contract will be sent by DEQ for electronic signature after the BCC approves it. MPH staff will alert DEQ to send… p. 1
- 4.Request board approve professional services agreement with Sapphire Mechanical for the cooling system upgrades project at the Missoula County Detention Facility. Total contract $1,356,000. - To provide construction services associated with the Cooling System Upgrades Project at the Missoula County Detention Facility. p. 1
- 5.Request board approve second addendum to interlocal agreement with the City of Missoula for construction and maintenance related to the stormwater system in the Missoula Development Park. - Request board approve and sign Second Addendum to Interlocal Agreement with the City of Missoula for construction and maintenance related to the stormwater system in the Missoula Development Park. Missoula County and the City of Missoula entered into an Interlocal Agreement on July 4, 2023, under which the County agreed to the following: Provide a conditions assessment and alternatives analysis which was completed on August 14, 2024. Construct improvements for the Missoula Development Park to ensure that the stormwater system functions to accommodate the 5-year, 24-hour storm event, which is the purpose of this Second Addendum. Document the intent of the County to transfer ownership and maintenance… p. 1
- 1.Request board appoint member to the Tax Appeal Board. - One partial term through March 31, 2027. Two applicant: Michael Paterni Daniel Lee Request board appoint member for a partial term beginning August 11, 2026, through March 31, 2027, to the Tax Appeal Board.
- 1.Letter 2026-183 to the Montana Department of Commerce requesting an exception to the rule to have only one CDBG Housing grant at a time, thus allowing Missoula County to apply for a housing grant on behalf of Opportunity Resources Inc. - Request board sign a letter to the Montana Department of Commerce requesting an exception to the rule to have only one CDBG Housing grant at a time, thus allowing Missoula County to apply for a housing grant on behalf of Opportunity Resources, Inc. ORI requires funding to rehabilitate their Howard Street Group Homes to ensure residents have safe, healthy and accessible places to live.