Agenda items (1)
- …tion to the Village Board related to the 2026 road projects. Kevin Risch, Clark Dietz Engineer, informed the committee that the goal is to be out for construction bid by mid-July in order to complete the construction still in 2026. The plans are 75% complete and the railroad and DNR permits for the watermain have been submitted. It is anticipated that it will be 4- 6 weeks before approval. The railroad additionally informed them that they cannot do the crossing pavements in 2026 due to budget constraints. Member Werner inquired as to how a waterline will go under the railroad. Engineer Risch i… p. 2