Committee on Ways and Means Agenda
1 item on this agenda matches the land-use topicsIndustrial land (1)
Agenda items (10)Show only the 1 matching
- 4. A resolution to approve an amendment of the Agreement for Development for Joint County Industrial Park, by and between Charleston County, South Carolina and Colleton County, South Carolina, so as to include additional property in the City of Charleston as part of the Joint County Industrial Park. (This item was considered by the Committee on Real Estate on September 21, 2026. This item is being brought forward to the Committee on Ways and Means due to time constraints) p. 1
- 3. Bids & Purchases p. 1
- 6. Facilities & Capital Projects – Capital Projects: Approval of Lowline Revised Early Site Package Scope of Work Change Order #5 to facilitate a remobilization date of 10/19/26. The Change Order amount is $2,006,204.00. This Change Order must be approved by COB September 22, 2026 to maintain revised Early Site Package construction package. This will be funded by the Cooper River Bridge TIF. p. 1
- 7. Facilities & Capital Projects – Parks: Approval of Joseph P. Riley, Jr., Ballpark Field Improvements Construction Contract with Carolina Green Corp in the amount of $1,372,870.00 as a part of the Joe Riley Ballpark Field Improvements project. The scope of this project includes turf removal and replacement, drainage systems scoping, and field raising. With approval of the project budget, staff is authorized to award and/or amend contracts less than $100,000.00 to the extent contingency funds exist in the Council Approved Budget. This work must be completed before the beginning of the 2027 ba… p. 1
- enhance the site at 1 Windsor Drive in West Ashley. With approval of the project budget, staff is authorized to award and/or amend contracts less than $100,000.00 to the extent contingency funds exist in the Council Approved Budget. Approval of this contract obligates $255,956.00 of the $400,000.00 project budget. The funding source for this project is: General Fund Reserves ($400,000.00). p. 2
- 9. Facilities & Capital Projects – Parks: Approval of Johns Island Recreation Center Guaranteed Maximum Price (GMP) Amendment #2 to the CMAR contract with Trident Construction LLC in the amount of $11,154,647.00 for an early release GMP package for the timely mobilization, delegated design, and procurement of goods and supplies for the Johns Island Recreation Center project. A final GMP amount and construction timeline will be brought to Council at a later date. Approval of GMP Amendment #2 will increase the CMAR contract by $11,154,647.00 (from $7,731,848.00 to $18,886,495.00). The funding so… p. 2
- …n project. The scope of this contract includes renovations to the existing concrete tennis court at Hazel Parker Playground, 70 East Bay Street. With approval of the project budget, staff is authorized to award and/or amend contracts less than $100,000.00 to the extent contingency funds exist in the Council Approved Budget. Approval of this contract obligates $177,010.00 of the $550,000.00 project budget. Funding sources for this project are: state Accommodations Tax ($300,000.00) and Hospitality Fund ($250,000.00). p. 2
- 11. Facilities & Capital Projects – Parks: Approval of WL Stephens Aquatic Center & Forest Park Playground Professional Services Contract for Special Inspections with S&ME in the amount of $100,000.00 for Construction Materials Testing and Special Inspections as a part of the WL Stephens Aquatic Center project. The scope of services includes evaluations, observations, and testings of Concrete, Piers, Masonry, and other construction materials, as well as erosion control inspections and project management pursuant to said work. Approval of this contract will obligate $100,000.00 of the project b… p. 2
- 13. Planning, Permitting, & Engineering – Stormwater Management: Approval of a 1-year maintenance service agreement contract extension with Harper General Contractors, Inc. in the amount of $420,000.00 for the continued maintenance of the Lockwood Drive/ William Dudley Gregorie Pump Station. The current contract expires on October 24, 2026. Approval of the contract extension does not obligate the City to any expenditures but will continue to utilize the Lockwood Drive Pump Station line item in the Stormwater Operations Budget. The contract amount is $420,000.00 and is included in the 2027 Stor… p. 2
- and tidal and flood resiliency in the Central Park Road basin on James Island. With approval of the project budget, staff is authorized to award and/or amend contracts less than $100,000.00 to the extent contingency funds exist in the Council Approved Budget. Approval of this contract obligates $4,504,395.48 of the $6,500,000.00 project budget. Funding sources for this project are: Drainage Fund ($5,000,000.00) and the SC Rural Infrastructure Authority ($1,500,000.00). (This item is being brought forward to the Committee on Ways & Means due to time constraints) In accordance with the Americans… p. 3
6 more passages from inside the staff reports, forms and minutes attached to this agenda are not listed as agenda items. Search finds every word of them.