GovMeet
Sign in

Feed › Wisconsin › Village of Mount Pleasant

Met Jan 22, result not posted yet

Land-use plan change, 241 acres — Mount Pleasant

Village of Mount Pleasant, Plan Commission. Comp plan, Site plan. First seen on an agenda Nov 14, 2026.

  1. On an agendaJan 22, 2025
  2. Last meetingPlan Commission, Wed Feb 19, 2025 14 meetings so far
  3. DecisionNot posted yet Minutes often come weeks after the meeting
241acres
14meetings on record
28days from first agenda to last

Track this case

From govmeet.us/app/case/9945993, November 23, 2026

The line on the agenda

Staff Review and Recommendation to the Plan Commission January 22, 2025 4811 CTH H Site Plan Review Application Request Site Plan Review Current Land Use Business Application Number SP-24-27 Future land use (from Comprehensive Plan) Business Applicant Name and Company (if applicable) Kevin Lynch, American Transmission Company Public Hearing Required? No Location 4811 CTH H Distance to Nearest Public Park Parcel ID 151-03-22-33-014-001 Distance to Nearest School Property Owner Microsoft Corporation Floodplain? No Parcel Size 241.29 acres Proposed Use: Utilities and public services, major Size o…

Plan Commission, January 22, 2025. Agenda, p. 3 · Minutes · Meeting page.

The record

Every value links to the agenda or minutes line it came from: tap “from the agenda” to read it.

Case numbers
SP-24-27
Acres
241read from the agenda line
13 more fields not read from the filing yet

Request, zoning, units, square feet, conditions, votes, applicant, owner, developer, engineer, attorney, parcel, where, amount. These fill in when the filing is read.

Filings on agendas ahead are read as they are posted. An older one is read on request on a paid plan. Prices

Every case is read for the same fields, so two cases always line up. Wrong or missing? Use “Report a mistake”; we check reports within 48 hours.

Who is behind it

The agenda line names it; it does not say in what role.

Every step, from the agendas and minutes

  1. Jan 22, 2025

    Plan Commission

    1. 4811 CTH H Site Plan Review; SP-24-27 Agenda page, p. 1 · This item

  2. Jan 22, 2025

    Plan Commission

    Agenda page, p. 3

  3. Jan 22, 2025

    Plan Commission

    SP-24-27 Area Zoning Area Future Land Use Application Summary Kevin Lynch, on behalf of American Transmission Company (ATC), applied to construct a 12-acre electrical substation. ATC will own, operate Agenda page, p. 4 · This item

  4. Jan 22, 2025

    Plan Commission

    SP-24-27 Site History # Type Date Submitted Status ZVA-24-9 Zoning Variances Dec. 19, 2024 Active SP-24-27 Site Plan Review Dec. 19, 2024 Active BLDG-24-262 Building Permit – Residential & Commercial Agenda page, p. 5 · This item

  5. Jan 22, 2025

    Plan Commission

    SP-24-27 comments, the applicant must revise the site plan in accordance with those conditions and comments and resubmit the plan for review. The Community Development Director must act on all resubmi Agenda page, p. 7 · This item

  6. Jan 22, 2025

    Plan Commission

    7. The Community Development Director will retain a copy of the approved site plan in the Department's permanent files. Recommendation The village staff recommends that the Plan Commission moves to re Agenda page, p. 7 · This item

  7. Jan 27, 2025

    Village Board

    5. Approval of 4811 CTH H Site Plan Review; SP-24-27 Agenda page, p. 1 · This item

  8. Jan 27, 2025

    Village Board

    Plan Commission Recommendation to the Village Board January 27, 2025 4811 CTH H Site Plan Review Application Request Site Plan Review Current Land Use Business Application Number SP-24-27 Future land Agenda page, p. 20 · This item

  9. Jan 27, 2025

    Village Board

    SP-24-27 Area Zoning Area Future Land Use Application Summary Kevin Lynch, on behalf of American Transmission Company (ATC), applied to construct a 12-acre electrical substation. ATC will own, operate Agenda page, p. 21 · This item

  10. Jan 27, 2025

    Village Board

    SP-24-27 Site History # Type Date Submitted Status ZVA-24-9 Zoning Variances Dec. 19, 2024 Active SP-24-27 Site Plan Review Dec. 19, 2024 Active BLDG-24-262 Building Permit – Residential & Commercial Agenda page, p. 22 · This item

  11. Jan 27, 2025

    Village Board

    SP-24-27 comments, the applicant must revise the site plan in accordance with those conditions and comments and resubmit the plan for review. The Community Development Director must act on all resubmi Agenda page, p. 24 · This item

  12. Jan 27, 2025

    Village Board

    7. The Community Development Director will retain a copy of the approved site plan in the Department's permanent files. Recommendation The Plan Commission recommends that the Village Board approves SP Agenda page, p. 24 · This item

  13. Feb 10, 2025

    Village Board

    5. Approval of 4811 CTH H Site Plan Review; SP-24-27 Agenda page, p. 2 · This item

  14. Feb 19, 2025

    Plan Commission

    1. 4811 CTH H Site Plan Review; SP-24-27 Community Development Director Sam Schultz explained that Kevin Lynch, on behalf of American Transmission Company (ATC), applied to construct a 12-acre electri Agenda page, p. 2 · This item