City of Inver Grove Heights, City Council. Industrial, Site plan. First seen on an agenda Nov 7, 2026.
- On an agendaApr 7
- Last meetingCity Council, Mon Sep 28 6 meetings so far
- DecisionNot posted yet Minutes often come weeks after the meeting
From govmeet.us/app/case/711172, November 22, 2026
The line on the agenda
Consider Major Site Plan Request for Development of an Approximately 54,070-Square Foot Data Center Located at 5890 Carmen Avenue.
City Council Regular Meeting Including 6/26, June 22, 2026. Agenda, p. 2 · Recording · Meeting page.
The record
What the filing states, field by field.
15 more fields not read from the filing yet
Case numbers, request, zoning, acres, units, square feet, conditions, votes, applicant, owner, developer, engineer, attorney, parcel, where, amount. These fill in when the filing is read.
Filings on agendas ahead are read as they are posted. An older one is read on request on a paid plan. Prices
Every case is read for the same fields, so two cases always line up. Wrong or missing? Use “Report a mistake”; we check reports within 48 hours.
Every step, from the agendas and minutes
- Apr 7
Planning Commission
Consider a Request for Approval of a Major Site Plan Review of the Proposed Development of an Approximately 55,000-Square-Foot Data Center Located at 5890 Carmen Ave. - CASE NO: 26-09SP APPLICANT: Kim Agenda page, p. 1 · Recording · This item · found by its address
- Apr 27
City Council
Agenda page, p. 2 · Recording · This item · found by its address
- May 26
City Council
Agenda page, p. 2 · Recording · This item · found by its address
- Jun 22
City Council
- Jul 27
City Council
Citizen Petition Review for Environmental Assessment Worksheet for Proposed Data Center at 5890 Carmen Avenue. Agenda page, p. 1 · Recording · This item · found by its address
- Sep 28
City Council
Resolution approving Major Site Plan Review for a data center at 5890 Carmen Avenue Agenda page, p. 2 · Recording · This item · found by its address
Earlier cases like this in City of Inver Grove Heights
36 earlier cases of the same kind on its agendas since 2022.
- Oct 2026Authorize the Hire of a Consulting Firm to Assist with the Data Center Moratorium Study.
- Sep 2026Resolution approving Major Site Plan Review for a data center at 5890 Carmen Avenue
- Sep 2026Moratorium Study Plan Related to Interim Ordinance Regarding Data Center Development.
- Aug 2026Data Center Litigation Update and First Reading of Ordinance Amending Existing Interim Ordinance
- Jul 2026Citizen Petition Review for Environmental Assessment Worksheet for Proposed Data Center at 5890 Carmen Avenue.
- Jun 2026Resolutions Approving a Major Site Plan Review and Conditional Use Permit Amendment for Two Mini-Storage…