Data Center Moratorium

Town of Schley, Planning Commission. Industrial, Moratorium. First seen on an agenda Nov 3, 2026.

  1. On an agendaAug 20
  2. Last meetingPlanning Commission, Thu Aug 20
  3. DecisionNot posted yet Minutes often come weeks after the meeting

Track this case

From govmeet.us/app/case/587200, November 22, 2026

The line on the agenda

C) Data Center Moratorium

Plan Commission, August 20, 2026. Agenda, p. 1 · Minutes · Meeting page.

The record

What the filing states, field by field.

15 more fields not read from the filing yet

Case numbers, request, zoning, acres, units, square feet, conditions, votes, applicant, owner, developer, engineer, attorney, parcel, where, amount. These fill in when the filing is read.

Filings on agendas ahead are read as they are posted. An older one is read on request on a paid plan. Prices

Every case is read for the same fields, so two cases always line up. Wrong or missing? Use “Report a mistake”; we check reports within 48 hours.

From the minutes

Result
Recommended approval
Vote
Roll call vote was conducted. All Ayes. Motion carried.
Recommended
Commission recommended the Town Board request the County Board implement a 12-month data center moratorium
Conditions
  • 12-month duration
M/S Dallman/Ratajczyk to recommend the Town Board request the County Board implement a 12 month moratorium on data centers to prevent potential Conditional Uses and allow county officials time to gather information to make more informed decisions. Roll call vote was conducted. All Ayes. Motion carri