Met Aug 17, result not posted yet

Moratorium — Genoa

Township of Genoa, Township Board of Trustees. Industrial, Moratorium. First seen on an agenda Nov 11, 2026.

  1. On an agendaAug 17
  2. Last meetingTownship Board of Trustees, Mon Aug 17
  3. DecisionNot posted yet Minutes often come weeks after the meeting

Track this case

From govmeet.us/app/case/4014291, November 22, 2026

The line on the agenda

11) Consideration of Resolution 260817B to extend the temporary Moratorium on the Acceptance and Approval of Applications for Data Centers and Cryptocurrency Mining Facilities within Genoa Charter Township for an additional six (6) months. (Roll Call)

Township Board of Trustees, August 17, 2026. Agenda, p. 1 · Minutes · Meeting page.

The record

What the filing states, field by field.

15 more fields not read from the filing yet

Case numbers, request, zoning, acres, units, square feet, conditions, votes, applicant, owner, developer, engineer, attorney, parcel, where, amount. These fill in when the filing is read.

Filings on agendas ahead are read as they are posted. An older one is read on request on a paid plan. Prices

Every case is read for the same fields, so two cases always line up. Wrong or missing? Use “Report a mistake”; we check reports within 48 hours.

From the minutes

Result
Approved · Vote 7–0
Vote
Moved by Hunt, supported by Hovarter, to approve Resolution No. 260817-B to extend the temporary moratorium on the acceptance and approval of applications for data centers and cryptocurrency mining facilities. The motion carried unanimously with a roll call vote (Valenti - yes; Hovarter - yes; Walker - yes; Reiber - yes; Hunt - yes; Soucy - yes; Spicher - yes)

Yes: Valenti, Hovarter, Walker, Reiber, Hunt, Soucy, Spicher. Every member's votes

Recommended
Staff asked for an additional six months to review a noise study, ensure ordinance enforceability, finalize drafts, and conduct public hearings.
Conditions
  • Extend temporary moratorium on data centers and cryptocurrency mining facilities by six months
Moved by Hunt, supported by Hovarter, to approve Resolution No. 260817-B to extend the temporary moratorium on the acceptance and approval of applications for data centers and cryptocurrency mining facilities. The motion carried unanimously with a roll call vote

Read from the meeting's minutes by AI; the quote is copied from them.

Every step, from the agendas and minutes

  1. Aug 17

    Township Board of Trustees

    Agenda page, p. 1