Special use permit, 249 acres — Imperial County
Imperial County, Planning Commission. Special use, Variance. First seen on an agenda Nov 11, 2026.
- On an agendaSep 24, 2025
- Last meetingPlanning Commission, Wed Sep 24, 2025
- DecisionNot posted yet Minutes often come weeks after the meeting
From govmeet.us/app/case/4003676, November 22, 2026
The line on the agenda
1. Recommend to the Board of Supervisors Variance #24-0004, for the Big Rock 2 Cluster Solar and Battery Storage project. 7l. Consideration of Conditional Use Permit #24-0009, Big Rock 2 Cluster West totaling 249 acres, which consists of the construction and operation of a utility-scale up to 80- megawatt (MW) in capacity photovoltaic (PV) solar energy generation and Battery Energy Storage System (BESS) facility (up to 60-MW in capacity). CUP#24-0009 is one of four CUPs being considered for simultaneous approval that would not exceed up to 500-MW for the PV portion, nor exceed 500-MW of associ…
Planning Commission, September 24, 2025. Agenda, p. 8 · Meeting page.
The record
What the filing states, field by field.
- Acres
- 249read from the agenda line
14 more fields not read from the filing yet
Case numbers, request, zoning, units, square feet, conditions, votes, applicant, owner, developer, engineer, attorney, parcel, where, amount. These fill in when the filing is read.
Filings on agendas ahead are read as they are posted. An older one is read on request on a paid plan. Prices
Every case is read for the same fields, so two cases always line up. Wrong or missing? Use “Report a mistake”; we check reports within 48 hours.
Every step, from the agendas and minutes
- Sep 24, 2025
Planning Commission