Pine County, County Board. Industrial, Moratorium. First seen on an agenda Nov 11, 2026.
- On an agendaApr 7
- Last meetingCounty Board, Tue Aug 18 7 meetings so far
- DecisionNot posted yet Minutes often come weeks after the meeting
From govmeet.us/app/case/3980372, November 22, 2026
The line on the agenda
8. Data Center Moratorium Consider adopting Pine County Ordinance 2026-15, an Interim Ordinance authorizing a study and placing a moratorium on data center developments. Authorize Board Chair and County Administrator to sign.
County Board, April 7, 2026. Agenda, p. 9 · Minutes · Meeting page.
The record
Every value links to the agenda or minutes line it came from: tap “from the agenda” to read it.
- Case numbers
- Ord. 2026-15
Data Center Moratorium Consider adopting Pine County Ordinance 2026-15, an Interim Ordinance authorizing a study and placing a moratorium on data center developments.
14 more fields not read from the filing yet
Request, zoning, acres, units, square feet, conditions, votes, applicant, owner, developer, engineer, attorney, parcel, where, amount. These fill in when the filing is read.
Filings on agendas ahead are read as they are posted. An older one is read on request on a paid plan. Prices
Every case is read for the same fields, so two cases always line up. Wrong or missing? Use “Report a mistake”; we check reports within 48 hours.
Every step, from the agendas and minutes
- Apr 7
County Board
1. Regular Agenda 8: Data Center Moratorium Pine County Ordinance 2026-15. Agenda page, p. 1 · This item
- Apr 7
County Board
PAGE 1 Pine County, Minnesota Ordinance #2026-15 Ordinance Amending Authorizing a Study and Placing a Moratorium on Data Centers in the County of Pine The Board of Commissioners of Pine County, Minnes Agenda page, p. 4 · This item
- Apr 7
County Board
- Jul 7
County Board
4. Data Center Moratorium (15 minutes) Consider adopting Pine County Ordinance 2026-15, an Interim Ordinance authorizing a study and placing a moratorium on data center developments. Authorize Board C Agenda page, p. 27 · This item
- Jul 21
County Board
1. Regular Agenda #6.1: Data Center Moratorium Public Hearing Consider setting a public hearing starting at or as close to 10:00 a.m. as possible, August 18, 2026, at the North Pine Government Center, Agenda page, p. 1 · This item
- Jul 21
County Board
COUNTY BOARD AGENDA REQUEST Date of Meeting: July 21, 2026 Consent Agenda Regular Agenda Item Title: Schedule Public Hearing – Data Center Moratorium Department: Administrator Department Head signatur Agenda page, p. 2 · This item
- Aug 18
County Board
F. Consider reaffirming the adoption of Pine County Ordinance 2026-15, an Interim Ordinance authorizing a study and placing a moratorium on data center developments. Agenda page, p. 6 · This item