Feed › California › Fresno County
Special use permit, 2,000 acres — Fresno County
Fresno County, Board of Supervisors. Special use. First seen on an agenda Nov 11, 2026.
- On an agendaFeb 11, 2025
- Last meetingBoard of Supervisors, Tue Feb 11, 2025
- DecisionDenied Feb 11
Track record: Fresno County approved 40 of 46 special uses decided since 2021 (87%).
From govmeet.us/app/case/3505615, November 22, 2026
The line on the agenda
…an appeal of Planning Commission’s approval of Unclassified Conditional Use Permit No. 3677 proposing to allow construction, operation, maintenance, and decommissioning of Sonrisa Solar Project (Project), of a photovoltaic (PV) solar electricity facility generating up to 200 megawatts and an energy storage facility with a capacity of approximately 184 megawatts, on approximately 2,000 acres; Project also proposes to include an approximately 0.2-mile gen-tie connection to an existing 3.3-mile long 230 kilovolt (kV) gen-tie through an adjacent existing energy project which connects to Tranquillity Switching Station, which is operated by Pacific Gas and Electric Company (PG&E); and if appeal is denied and Planning Commission’s approval of Unclassified Conditional Use Permit No. 3677 is upheld, Board should adopt the proposed resolution consisting of the following actions: a. find that the Final Environmental Impact Report (FEIR) was presented to, reviewed, and considered by the Board; b. find that decision to certify the FEIR reflects the Board’s independent judgment; c. adopt California Environmental Quality Act (CEQA) Findings of Fact, approve Mitigation Monitoring and Reporting…
Board of Supervisors, February 11, 2025. Agenda, p. 4 · Minutes · Meeting page.
The record
What the filing states, field by field.
- Case numbers
- 24-1430
- Acres
- 2,000read from the agenda line
13 more fields not read from the filing yet
Request, zoning, units, square feet, conditions, votes, applicant, owner, developer, engineer, attorney, parcel, where, amount. These fill in when the filing is read.
Filings on agendas ahead are read as they are posted. An older one is read on request on a paid plan. Prices
Every case is read for the same fields, so two cases always line up. Wrong or missing? Use “Report a mistake”; we check reports within 48 hours.
Who is behind it
- Named in the agenda linePacific Gas and Electric Company
Pacific Gas and Electric Company on other agendas · Alert me when it is named again · State registry · LinkedIn · Web
The agenda line names it; it does not say in what role.
Every step, from the agendas and minutes
- Feb 11, 2025
Board of Supervisors: Denied