Township of Watersmeet. Industrial, Moratorium. First seen on an agenda Oct 26, 2026.

  1. On an agendaOct 1
  2. Last meetingMeeting, Thu Oct 1
  3. DecisionNot posted yet Minutes often come weeks after the meeting

Track this case

From govmeet.us/app/case/270832, November 22, 2026

The line on the agenda

a. Data Center Moratorium next steps

Meetings, October 1, 2026. Agenda, p. 1 · Minutes · Meeting page.

The record

What the filing states, field by field.

15 more fields not read from the filing yet

Case numbers, request, zoning, acres, units, square feet, conditions, votes, applicant, owner, developer, engineer, attorney, parcel, where, amount. These fill in when the filing is read.

Filings on agendas ahead are read as they are posted. An older one is read on request on a paid plan. Prices

Every case is read for the same fields, so two cases always line up. Wrong or missing? Use “Report a mistake”; we check reports within 48 hours.

From the minutes

Result
Recommended approval
Vote
Motion passed with all ayes.
Recommended
Planning Commission recommends the Township Board direct its attorney to draft regulations governing data centers
The Planning Commission recommends that the Watersmeet Township Board direct its attorney (ST) to draft the necessary regulations governing data center(s) in Watersmeet Township. A motion was made to support this by David Susoreny. A second was offered by Simon Zelinski. The motion passed with all a

Read from the meeting's minutes by AI; the quote is copied from them.

Every step, from the agendas and minutes

  1. Oct 1

Earlier cases like this in Township of Watersmeet

4 earlier cases of the same kind on its agendas since 2026.

Every meeting of Township of Watersmeet, by year