The line on the agenda
8. IBM – BUILDING 003 QUANTUM SYSTEM II – PHASE II SEQRA Review, Coastal Consistency Review, Amended Site Plan Review, and Architectural Review for construction of a concrete pad for the placement of one (1) new chiller unit. The application also includes parking area restriping, equipment coordination, installation of an equipment enclosure and the replacement of two (2) existing temporary generators with two (2) permanent generators. In addition, the existing asphalt mound paving located beneath the temporary containment areas will be removed to allow the area to be re-graded to be flush wit…
September 17, 2026 Planning Board Meeting Agenda, September 17, 2026. Agenda, p. 3 · Minutes · Meeting page.
The record
What the filing states, field by field.
15 more fields not read from the filing yet
Case numbers, request, zoning, acres, units, square feet, conditions, votes, applicant, owner, developer, engineer, attorney, parcel, where, amount. These fill in when the filing is read.
Filings on agendas ahead are read as they are posted. An older one is read on request on a paid plan. Prices
Every case is read for the same fields, so two cases always line up. Wrong or missing? Use “Report a mistake”; we check reports within 48 hours.
From the minutes
- Result
- Approved with conditions · Vote 6–0
- Vote
- Motion carried 6-0 (Moved: Nicole Gemmati; Seconded: Rocco Romeo). Motion to grant: Moved: Nicole Gemmati; Seconded: Rocco Romeo; Carried: 6-0.
- Conditions
- Respond to Planning Board and Town department comments
- Respond to Planning Department comments dated September 11, 2026
- Respond to Engineering Department comments dated September 9, 2026
- Respond to Zoning Department comments dated September 8, 2026
- Respond to Building Department comments dated September 8, 2026
- Respond to Arlington Fire Department comments dated September 7, 2026
- Respond to Water Department comments dated September 1, 2026
- Respond to Sewer Department comments dated August 26, 2026
A motion was made that the Planning Board grant for IBM Building 003 Quantum System II – Phase II, subject to the following:
Read from the meeting's minutes by AI; the quote is copied from them.
Every step, from the agendas and minutes
- Aug 20
Planning Board
- Sep 17
Planning Board
Earlier cases like this in Town of Poughkeepsie
277+ earlier cases of the same kind on its agendas since 2024.
- Nov 2026ADAMS FAIRACRE FARMS – RENOVATION AND EXPANSION SEQRA Review, Site Plan Review, and Architectural Review…
- Nov 2026MARIST UNIVERSITY – SCIENCE BUILDING ADDITION Site Plan Review and Architectural Review for the…
- Nov 2026MARIST UNIVERSITY – 69 W CEDAR STREET AND 74 W CEDAR STREET SEQRA Review and Amended Site Plan Review for…
- Nov 2026759 MAIN STREET Special Use Permit Review, Site Plan Review, and Architectural Review for the proposal of…
- Nov 2026SELF-STORAGE – 2345 SOUTH ROAD SEQRA Review, Special Use Permit Review, Site Plan Review, Architectural…
- Nov 2026SALT POINT CENTER Time Extension of a conditionally approved special use permit, site plan and aquatic…