Feed › Wisconsin › Ozaukee County
Industrial — Ozaukee County
Ozaukee County, Executive Committee. Industrial. First seen on an agenda Nov 25, 2026.
- On an agendaJan 7
- Next meetingExecutive Committee, Mon Nov 30, 3:00 PM in 5 days Agenda page, p. 12 meetings so far
- DecisionNot yet Read from the minutes after the vote
From govmeet.us/app/case/10759373, November 25, 2026
The line on the agenda
…ATC’s September 2026 revised application addresses regional electric demand, including the Port Washington data center. The project includes new and rebuilt 345-kilovolt transmission lines, facility upgrades, and new substations. ATC identifies South East as its preferred southern route. The alternate South West route includes a new dual-circuit 345-kilovolt line extending from the Town of Saukville through the Fredonia area toward Farmington. ATC states that both southern routes primarily use existing power line corridors, although additional rights-of-way may still be needed.
Executive Committee - Administration Center, November 30, 2026. Agenda, p. 1 · Meeting page.
How to take part
- In person: Administration Center Room A-200
- Written comments:
The public can submit comments here: Public Comment Form Public Comment Policy & Instructions For Submitting Public Comments Online AGENDA
agenda p. 1
Quoted from the agenda; rules change, so check its first pages before you go. Agenda, first page.
Draft a public comment
The AI writes a short letter to the board from this case's facts; you edit it and send it. Sign in to draft one (free).
The record
Every value links to the agenda or minutes line it came from: tap “from the agenda” to read it.
- Case numbers
- Res. 25-50
stribution Interconnection Project Utilizing the Identified South East Transmission Route - The proposed resolution is a companion to the County Board’s resolutions adopted January 7, 2026, including Resolution No. 25-50 supporting the use of existing transmission corridors.
14 more fields not read from the filing yet
Request, zoning, acres, units, square feet, conditions, votes, applicant, owner, developer, engineer, attorney, parcel, where, amount. These fill in when the filing is read.
Every case is read for the same fields, so two cases always line up. Wrong or missing? Use “Report a mistake”; we check reports within 48 hours.
Who is behind it
- Named in the agenda lineSupporting American Transmission Company
Supporting American Transmission Company on other agendas · Alert me when it is named again · State registry · LinkedIn · Web
The agenda line names it; it does not say in what role.
Every step, from the agendas and minutes
- Jan 7
County Board
Resolution 25-50: Supporting American Transmission Company’s Ozaukee County Distribution Interconnection Project Utilizing the Identified Alternate Transmission Route - Resolution was approved by the Agenda page, p. 1 · Recording · This item
- Nov 30
Executive Committee, coming up