Feed › California › City of El Paso De Robles

Met Jul 8, result not posted yet

Planned development, 4.84 acres — El Paso De Robles

City of El Paso De Robles, Planning Commission. PUD, Special use. First seen on an agenda Nov 18, 2026.

  1. On an agendaMay 23, 2023
  2. Last meetingPlanning Commission, Tue Jul 8, 2025 20 meetings so far
  3. DecisionNot posted yet Minutes often come weeks after the meeting
4.84acres
20meetings on record
777days from first agenda to last

Track this case

From govmeet.us/app/case/10235895, November 23, 2026

The line on the agenda

2. Time Extension for the Firestone Solar Project P22-0128 66 Request for approval of a time extension of the entitlements associated with Planned Development 22-21 and Conditional Use Permit 22-21, to construct a 1.2-megawatt (MW) solar ground-mounted single axis tracker system on approximately 4.84-acres within a 13.75-acre field (P22-0128 / PD 22-21 / CUP 22-21 / TEX 25-03). Address: Northern end of Ramada Drive/east of US Hwy 101 / APN: 009-631- 018 Applicant: REC Solar CEQA Determination: The project is consistent with the approved environmental document. Recommended: Approve Draft Resolu…

Planning Commission, July 8, 2025. Agenda, p. 2 · Meeting page.

The record

What the filing states, field by field.

Acres
4.84read from the agenda line
14 more fields not read from the filing yet

Case numbers, request, zoning, units, square feet, conditions, votes, applicant, owner, developer, engineer, attorney, parcel, where, amount. These fill in when the filing is read.

Filings on agendas ahead are read as they are posted. An older one is read on request on a paid plan. Prices

Every case is read for the same fields, so two cases always line up. Wrong or missing? Use “Report a mistake”; we check reports within 48 hours.

Every step, from the agendas and minutes

  1. May 23, 2023

    Planning Commission

    City of Paso Robles Planning Commission Agenda Report From: Darcy Delgado, Associate Planner Subject: Planned Development (PD22-21), Conditional Use Permit (CUP22-21) Northern end of Ramada Drive/east Agenda page, p. 5 · This item

  2. May 23, 2023

    Planning Commission

    4. Draft Resolution B (PD 22-21, CUP 22-21) Agenda page, p. 7 · This item

  3. May 23, 2023

    Planning Commission

    …3) AND MITIGATION MONITORING AND REPORTING PLAN PURSUANT TO THE CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA) FOR THE FIRESTONE SOLAR PROJECT PHASE II (PLANNED DEVELOPMENT 22-21, CONDITIONAL USE PERMIT Agenda page, p. 10 · This item

  4. May 23, 2023

    Planning Commission

    Attachment 3 Mitigation Monitoring Program – Mitigation Measure PD22-21, CUP22-21 (Firestone Solar Project) Type Monitoring Department or Agency Shown on Plans Verified Implementation Timing/Remarks r Agenda page, p. 15 · This item

  5. May 23, 2023

    Planning Commission

    Attachment 3 Mitigation Monitoring Program – Mitigation Measure PD22-21, CUP22-21 (Firestone Solar Project) Type Monitoring Department or Agency Shown on Plans Verified Implementation Timing/Remarks t Agenda page, p. 16 · This item

  6. May 23, 2023

    Planning Commission

    Attachment 3 Mitigation Monitoring Program – Mitigation Measure PD22-21, CUP22-21 (Firestone Solar Project) Type Monitoring Department or Agency Shown on Plans Verified Implementation Timing/Remarks h Agenda page, p. 17 · This item

  7. May 23, 2023

    Planning Commission

    Attachment 3 Mitigation Monitoring Program – Mitigation Measure PD22-21, CUP22-21 (Firestone Solar Project) Type Monitoring Department or Agency Shown on Plans Verified Implementation Timing/Remarks i Agenda page, p. 18 · This item

  8. May 23, 2023

    Planning Commission

    Attachment 3 Mitigation Monitoring Program – Mitigation Measure PD22-21, CUP22-21 (Firestone Solar Project) Type Monitoring Department or Agency Shown on Plans Verified Implementation Timing/Remarks w Agenda page, p. 19 · This item

  9. May 23, 2023

    Planning Commission

    Attachment 3 Mitigation Monitoring Program – Mitigation Measure PD22-21, CUP22-21 (Firestone Solar Project) Type Monitoring Department or Agency Shown on Plans Verified Implementation Timing/Remarks Agenda page, p. 20 · This item

  10. May 23, 2023

    Planning Commission

    Attachment 3 Mitigation Monitoring Program – Mitigation Measure PD22-21, CUP22-21 (Firestone Solar Project) Type Monitoring Department or Agency Shown on Plans Verified Implementation Timing/Remarks B Agenda page, p. 21 · This item

  11. May 23, 2023

    Planning Commission

    Attachment 3 Mitigation Monitoring Program – Mitigation Measure PD22-21, CUP22-21 (Firestone Solar Project) Type Monitoring Department or Agency Shown on Plans Verified Implementation Timing/Remarks B Agenda page, p. 22 · This item

  12. May 23, 2023

    Planning Commission

    Attachment 3 Mitigation Monitoring Program – Mitigation Measure PD22-21, CUP22-21 (Firestone Solar Project) Type Monitoring Department or Agency Shown on Plans Verified Implementation Timing/Remarks t Agenda page, p. 23 · This item

  13. May 23, 2023

    Planning Commission

    Attachment 3 Mitigation Monitoring Program – Mitigation Measure PD22-21, CUP22-21 (Firestone Solar Project) Type Monitoring Department or Agency Shown on Plans Verified Implementation Timing/Remarks e Agenda page, p. 24 · This item

  14. May 23, 2023

    Planning Commission

    Attachment 3 Mitigation Monitoring Program – Mitigation Measure PD22-21, CUP22-21 (Firestone Solar Project) Type Monitoring Department or Agency Shown on Plans Verified Implementation Timing/Remarks a Agenda page, p. 25 · This item

  15. May 23, 2023

    Planning Commission

    Attachment 3 Mitigation Monitoring Program – Mitigation Measure PD22-21, CUP22-21 (Firestone Solar Project) Type Monitoring Department or Agency Shown on Plans Verified Implementation Timing/Remarks I Agenda page, p. 26 · This item

  16. May 23, 2023

    Planning Commission

    Attachment 4 DRAFT RESOLUTION NO. PC 23-XXX (B) A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF EL PASO DE ROBLES TO APPROVE PLANNED DEVELOPMENT 22-21 & CONDITIONAL USE PERMIT 22-21 FOR THE FIR Agenda page, p. 29 · This item

  17. May 23, 2023

    Planning Commission

    …e the environmental findings and analysis set forth in Resolution No. 2023-__, including the MND, as if fully set forth herein. Section 4 - Approval: Planned Development 22-21 & CUP 22-21 is approved Agenda page, p. 31 · This item

  18. Jul 8, 2025

    Planning Commission

    06. Attachment 6 - Legal Affidavit.pdf Request for approval of a time extension of the entitlements associated with Planned Development 22-21 and Conditional Use Permit 22-21, to construct a 1.2-megaw Agenda page, p. 1 · This item

  19. Jul 8, 2025

    Planning Commission

    Agenda page, p. 2

  20. Jul 8, 2025

    Planning Commission

    RESOLUTION NO. PC 23-033 (B) A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF EL PASO DE ROBLES TO APPROVE PLANNED DEVELOPMENT 22-21 & CONDITIONAL USE PERMIT 22-21 FOR THE FIRESTONE SOLAR PROJEC Agenda page, p. 70 · This item